Въведение в курса · 3 мин

Измерване по IS 1200 и фактуриране (Индия)

You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.

Започнете задача 1

The RCC frame of a three-storey teaching block with bamboo scaffolding and green safety net, workers on the floor slabs, two women carrying head pans of mortar, and heaps of sand and aggregate in front.Измислен проект
Academic Block B, Sonapada InstituteRCC frame up, brickwork and plaster under way
Building
Ground plus two storey teaching block of a central institute
Contract
CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
Currency
Rupees, tendered rates inclusive of GST
Работа в ERP
Задачи: 5, около 2 ч 45 мин

Кой какво предава на кого

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Идва при вас

  • Project ManagerYour firm, your side
    • Wall CW1 and its opening sizesЗадача 1
    • The tender percentage the company quotedЗадача 3
  • Engineer-in-ChargeInstitute Engineering Wing
    • Cost index notified for the stationЗадача 3
    • RA Bill 1, passed for paymentЗадача 5
ВиеBilling engineer, your firm

Тръгва от вас

    • Brickwork measured to IS 1200Задача 1
    • Plaster measured to IS 1200Задача 2
    • RA Bill 1 and what is left to billЗадача 4
    Engineer-in-ChargeChecks measurements and bills
    • Recoveries and the amount payableЗадача 5
    Accounts officerInstitute, pays the bill

Вашият път през проекта

Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.

  1. Measure the wall

    Задача 1 · 35 мин

    Измерване на зидарията: кои отвори се приспадат

    Вашият резултат
    Brickwork volume of wall CW1 on line 2.3
    Документ
    Elevation of CW1 with seven openings
    В ERP
    Bill of Quantities
  2. Measure the wall

    Задача 2 · 35 мин

    Мазилка на същата стена: три прага, не един

    Вашият резултат
    Plaster area of the same wall on line 3.1
    Документ
    The same elevation, plaster on both faces
    В ERP
    Bill of Quantities
  3. Price and bill

    Задача 3 · 35 мин

    Остойностяване на обобщената ведомост: базови ставки, индекс на разходите, тръжен процент

    Вашият резултат
    Gross value of the abstract (the priced summary of all lines)
    Документ
    Schedule base rates and the station cost index
    В ERP
    Bill of Quantities
  4. Price and bill

    Задача 4 · 30 мин

    Междинна сметка 1 (running account bill) в ERP

    Вашият резултат
    RA Bill 1 (the first part payment) in five lines, the share billed and the balance
    Документ
    Contract: tendered amount and Schedule 'F'
    В ERP
    Contracts
  5. Get paid

    Задача 5 · 30 мин

    Приспадания: гаранционен депозит, такса за социално осигуряване, GST

    Вашият резултат
    The amount the institute pays
    Документ
    Passed RA Bill 1 and the tax position
    В ERP
    Contracts

From one wall to one payment

Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.

Brickwork, m³
Задача 1Brickwork by volumeOne face of the wall less the openings over 0.1 m², times the thickness, less the concrete (RCC) lintels over the openings.
Plaster, m²Brickwork, m³
Задача 2Plaster by areaBoth faces, openings deducted by size band, reveals added only for the largest.
Tender %Cost indexAbstract at base rates
Задача 3Base rates, then two additionsSchedule base rates on every line. The station cost index, the percentage for this location, on the base total; the tender percentage on the indexed total.
Gross of RA Bill 1
Задача 4The same money as a billFive lines in the claim. The gross is measured against the tendered amount, not the estimate.
Cess, GST TDSSecurity depositPaid to the contractor
Задача 5What reaches the bankSecurity deposit off the gross. The labour welfare cess and the GST tax deducted at source (TDS) come off the value without GST.

В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.

Накратко. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.