Измерване по IS 1200 и фактуриране (Индия)
You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.
Измислен проект- Building
- Ground plus two storey teaching block of a central institute
- Contract
- CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
- Currency
- Rupees, tendered rates inclusive of GST
- Работа в ERP
- Задачи: 5, около 2 ч 45 мин
Кой какво предава на кого
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Идва при вас
- Project ManagerYour firm, your side
- Wall CW1 and its opening sizesЗадача 1
- The tender percentage the company quotedЗадача 3
- Engineer-in-ChargeInstitute Engineering Wing
- Cost index notified for the stationЗадача 3
- RA Bill 1, passed for paymentЗадача 5
Тръгва от вас
- Brickwork measured to IS 1200Задача 1
- Plaster measured to IS 1200Задача 2
- RA Bill 1 and what is left to billЗадача 4
- Recoveries and the amount payableЗадача 5
Вашият път през проекта
Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.
Measure the wall
Задача 1 · 35 мин
Измерване на зидарията: кои отвори се приспадат
- Вашият резултат
- Brickwork volume of wall CW1 on line 2.3
- Документ
- Elevation of CW1 with seven openings
- В ERP
- Bill of Quantities
Measure the wall
Задача 2 · 35 мин
Мазилка на същата стена: три прага, не един
- Вашият резултат
- Plaster area of the same wall on line 3.1
- Документ
- The same elevation, plaster on both faces
- В ERP
- Bill of Quantities
Price and bill
Задача 3 · 35 мин
Остойностяване на обобщената ведомост: базови ставки, индекс на разходите, тръжен процент
- Вашият резултат
- Gross value of the abstract (the priced summary of all lines)
- Документ
- Schedule base rates and the station cost index
- В ERP
- Bill of Quantities
Price and bill
Задача 4 · 30 мин
Междинна сметка 1 (running account bill) в ERP
- Вашият резултат
- RA Bill 1 (the first part payment) in five lines, the share billed and the balance
- Документ
- Contract: tendered amount and Schedule 'F'
- В ERP
- Contracts
Get paid
Задача 5 · 30 мин
Приспадания: гаранционен депозит, такса за социално осигуряване, GST
- Вашият резултат
- The amount the institute pays
- Документ
- Passed RA Bill 1 and the tax position
- В ERP
- Contracts
From one wall to one payment
Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.
В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.
Накратко. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.