کورس کا تعارف · 3 منٹ

IS 1200 کے مطابق پیمائش اور بل (بھارت)

You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.

ٹاسک 1 شروع کریں

The RCC frame of a three-storey teaching block with bamboo scaffolding and green safety net, workers on the floor slabs, two women carrying head pans of mortar, and heaps of sand and aggregate in front.فرضی پراجیکٹ
Academic Block B, Sonapada InstituteRCC frame up, brickwork and plaster under way
Building
Ground plus two storey teaching block of a central institute
Contract
CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
Currency
Rupees, tendered rates inclusive of GST
ERP میں کام
5 ٹاسک، تقریباً 2 گھنٹے 45 منٹ

کون کس کو کیا دیتا ہے

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

آپ کے پاس آتا ہے

  • Project ManagerYour firm, your side
    • Wall CW1 and its opening sizesٹاسک 1
    • The tender percentage the company quotedٹاسک 3
  • Engineer-in-ChargeInstitute Engineering Wing
    • Cost index notified for the stationٹاسک 3
    • RA Bill 1, passed for paymentٹاسک 5
آپBilling engineer, your firm

آپ سے جاتا ہے

    • Brickwork measured to IS 1200ٹاسک 1
    • Plaster measured to IS 1200ٹاسک 2
    • RA Bill 1 and what is left to billٹاسک 4
    Engineer-in-ChargeChecks measurements and bills
    • Recoveries and the amount payableٹاسک 5
    Accounts officerInstitute, pays the bill

پراجیکٹ میں آپ کا راستہ

Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.

  1. Measure the wall

    ٹاسک 1 · 35 منٹ

    اینٹوں کی چنائی ناپیں: کون سے کھلے حصے منہا ہوتے ہیں

    آپ کا نتیجہ
    Brickwork volume of wall CW1 on line 2.3
    دستاویز
    Elevation of CW1 with seven openings
    ERP میں
    Bill of Quantities
  2. Measure the wall

    ٹاسک 2 · 35 منٹ

    اسی دیوار پر پلاسٹر: ایک نہیں، تین حدیں

    آپ کا نتیجہ
    Plaster area of the same wall on line 3.1
    دستاویز
    The same elevation, plaster on both faces
    ERP میں
    Bill of Quantities
  3. Price and bill

    ٹاسک 3 · 35 منٹ

    ایبسٹریکٹ کی قیمت لگائیں: بنیادی شرحیں، کاسٹ انڈیکس، ٹینڈر فیصد

    آپ کا نتیجہ
    Gross value of the abstract (the priced summary of all lines)
    دستاویز
    Schedule base rates and the station cost index
    ERP میں
    Bill of Quantities
  4. Price and bill

    ٹاسک 4 · 30 منٹ

    ERP میں رننگ اکاؤنٹ بل 1

    آپ کا نتیجہ
    RA Bill 1 (the first part payment) in five lines, the share billed and the balance
    دستاویز
    Contract: tendered amount and Schedule 'F'
    ERP میں
    Contracts
  5. Get paid

    ٹاسک 5 · 30 منٹ

    کٹوتیاں: سیکیورٹی ڈپازٹ، ویلفیئر سیس، GST

    آپ کا نتیجہ
    The amount the institute pays
    دستاویز
    Passed RA Bill 1 and the tax position
    ERP میں
    Contracts

From one wall to one payment

Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.

Brickwork, m³
ٹاسک 1Brickwork by volumeOne face of the wall less the openings over 0.1 m², times the thickness, less the concrete (RCC) lintels over the openings.
Plaster, m²Brickwork, m³
ٹاسک 2Plaster by areaBoth faces, openings deducted by size band, reveals added only for the largest.
Tender %Cost indexAbstract at base rates
ٹاسک 3Base rates, then two additionsSchedule base rates on every line. The station cost index, the percentage for this location, on the base total; the tender percentage on the indexed total.
Gross of RA Bill 1
ٹاسک 4The same money as a billFive lines in the claim. The gross is measured against the tendered amount, not the estimate.
Cess, GST TDSSecurity depositPaid to the contractor
ٹاسک 5What reaches the bankSecurity deposit off the gross. The labour welfare cess and the GST tax deducted at source (TDS) come off the value without GST.

نیلا وہ ہے جو ٹاسک شامل کرتا ہے؛ سرمئی پچھلے مرحلے سے آیا ہے۔

مختصراً. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.