Introduktion till kursen · 3 min
Mätning enligt IS 1200 och fakturering (Indien)
You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.
Fiktivt projekt- Building
- Ground plus two storey teaching block of a central institute
- Contract
- CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
- Currency
- Rupees, tendered rates inclusive of GST
- Arbete i ERP
- 5 uppgifter, cirka 2 h 45 min
Vem lämnar vad till vem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer till dig
- Project ManagerYour firm, your side
- Wall CW1 and its opening sizesUppgift 1
- The tender percentage the company quotedUppgift 3
- Engineer-in-ChargeInstitute Engineering Wing
- Cost index notified for the stationUppgift 3
- RA Bill 1, passed for paymentUppgift 5
Går från dig
- Brickwork measured to IS 1200Uppgift 1
- Plaster measured to IS 1200Uppgift 2
- RA Bill 1 and what is left to billUppgift 4
- Recoveries and the amount payableUppgift 5
Din väg genom projektet
Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.
Measure the wall
Uppgift 1 · 35 min
Mät tegelmurverket: vilka öppningar dras av
- Du tar fram
- Brickwork volume of wall CW1 on line 2.3
- Dokument
- Elevation of CW1 with seven openings
- I ERP
- Bill of Quantities
Measure the wall
Uppgift 2 · 35 min
Puts på samma vägg: tre gränsvärden, inte ett
- Du tar fram
- Plaster area of the same wall on line 3.1
- Dokument
- The same elevation, plaster on both faces
- I ERP
- Bill of Quantities
Price and bill
Uppgift 3 · 35 min
Prissätt sammanställningen: grundpriser, kostnadsindex, anbudsprocent
- Du tar fram
- Gross value of the abstract (the priced summary of all lines)
- Dokument
- Schedule base rates and the station cost index
- I ERP
- Bill of Quantities
Price and bill
Uppgift 4 · 30 min
Löpande räkning 1 i ERP:et
- Du tar fram
- RA Bill 1 (the first part payment) in five lines, the share billed and the balance
- Dokument
- Contract: tendered amount and Schedule 'F'
- I ERP
- Contracts
Get paid
Uppgift 5 · 30 min
Avdrag: säkerhetsdeposition, välfärdsavgift, GST
- Du tar fram
- The amount the institute pays
- Dokument
- Passed RA Bill 1 and the tax position
- I ERP
- Contracts
From one wall to one payment
Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.
Blått är det uppgiften lägger till; grått följer med från tidigare.
Kort sagt. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.