Introduktion till kursen · 3 min

Mätning enligt IS 1200 och fakturering (Indien)

You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.

Starta uppgift 1

The RCC frame of a three-storey teaching block with bamboo scaffolding and green safety net, workers on the floor slabs, two women carrying head pans of mortar, and heaps of sand and aggregate in front.Fiktivt projekt
Academic Block B, Sonapada InstituteRCC frame up, brickwork and plaster under way
Building
Ground plus two storey teaching block of a central institute
Contract
CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
Currency
Rupees, tendered rates inclusive of GST
Arbete i ERP
5 uppgifter, cirka 2 h 45 min

Vem lämnar vad till vem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer till dig

  • Project ManagerYour firm, your side
    • Wall CW1 and its opening sizesUppgift 1
    • The tender percentage the company quotedUppgift 3
  • Engineer-in-ChargeInstitute Engineering Wing
    • Cost index notified for the stationUppgift 3
    • RA Bill 1, passed for paymentUppgift 5
DuBilling engineer, your firm

Går från dig

    • Brickwork measured to IS 1200Uppgift 1
    • Plaster measured to IS 1200Uppgift 2
    • RA Bill 1 and what is left to billUppgift 4
    Engineer-in-ChargeChecks measurements and bills
    • Recoveries and the amount payableUppgift 5
    Accounts officerInstitute, pays the bill

Din väg genom projektet

Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.

  1. Measure the wall

    Uppgift 1 · 35 min

    Mät tegelmurverket: vilka öppningar dras av

    Du tar fram
    Brickwork volume of wall CW1 on line 2.3
    Dokument
    Elevation of CW1 with seven openings
    I ERP
    Bill of Quantities
  2. Measure the wall

    Uppgift 2 · 35 min

    Puts på samma vägg: tre gränsvärden, inte ett

    Du tar fram
    Plaster area of the same wall on line 3.1
    Dokument
    The same elevation, plaster on both faces
    I ERP
    Bill of Quantities
  3. Price and bill

    Uppgift 3 · 35 min

    Prissätt sammanställningen: grundpriser, kostnadsindex, anbudsprocent

    Du tar fram
    Gross value of the abstract (the priced summary of all lines)
    Dokument
    Schedule base rates and the station cost index
    I ERP
    Bill of Quantities
  4. Price and bill

    Uppgift 4 · 30 min

    Löpande räkning 1 i ERP:et

    Du tar fram
    RA Bill 1 (the first part payment) in five lines, the share billed and the balance
    Dokument
    Contract: tendered amount and Schedule 'F'
    I ERP
    Contracts
  5. Get paid

    Uppgift 5 · 30 min

    Avdrag: säkerhetsdeposition, välfärdsavgift, GST

    Du tar fram
    The amount the institute pays
    Dokument
    Passed RA Bill 1 and the tax position
    I ERP
    Contracts

From one wall to one payment

Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.

Brickwork, m³
Uppgift 1Brickwork by volumeOne face of the wall less the openings over 0.1 m², times the thickness, less the concrete (RCC) lintels over the openings.
Plaster, m²Brickwork, m³
Uppgift 2Plaster by areaBoth faces, openings deducted by size band, reveals added only for the largest.
Tender %Cost indexAbstract at base rates
Uppgift 3Base rates, then two additionsSchedule base rates on every line. The station cost index, the percentage for this location, on the base total; the tender percentage on the indexed total.
Gross of RA Bill 1
Uppgift 4The same money as a billFive lines in the claim. The gross is measured against the tendered amount, not the estimate.
Cess, GST TDSSecurity depositPaid to the contractor
Uppgift 5What reaches the bankSecurity deposit off the gross. The labour welfare cess and the GST tax deducted at source (TDS) come off the value without GST.

Blått är det uppgiften lägger till; grått följer med från tidigare.

Kort sagt. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.