Kursuse sissejuhatus · 3 min
Mõõtmine IS 1200 järgi ja arveldamine (India)
You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.
Väljamõeldud projekt- Building
- Ground plus two storey teaching block of a central institute
- Contract
- CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
- Currency
- Rupees, tendered rates inclusive of GST
- Töö ERP-s
- Ülesandeid 5, umbes 2 h 45 min
Kes annab kellele mida
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Tuleb sinule
- Project ManagerYour firm, your side
- Wall CW1 and its opening sizesÜlesanne 1
- The tender percentage the company quotedÜlesanne 3
- Engineer-in-ChargeInstitute Engineering Wing
- Cost index notified for the stationÜlesanne 3
- RA Bill 1, passed for paymentÜlesanne 5
Läheb sinult
- Brickwork measured to IS 1200Ülesanne 1
- Plaster measured to IS 1200Ülesanne 2
- RA Bill 1 and what is left to billÜlesanne 4
- Recoveries and the amount payableÜlesanne 5
Sinu tee läbi projekti
Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.
Measure the wall
Ülesanne 1 · 35 min
Mõõtke tellismüüritis: millised avad maha arvatakse
- Sinu tulemus
- Brickwork volume of wall CW1 on line 2.3
- Dokument
- Elevation of CW1 with seven openings
- ERP-s
- Bill of Quantities
Measure the wall
Ülesanne 2 · 35 min
Krohv samal seinal: kolm piirmäära, mitte üks
- Sinu tulemus
- Plaster area of the same wall on line 3.1
- Dokument
- The same elevation, plaster on both faces
- ERP-s
- Bill of Quantities
Price and bill
Ülesanne 3 · 35 min
Hinnastage eelarve: baashinnad, kuluindeks, pakkumise protsent
- Sinu tulemus
- Gross value of the abstract (the priced summary of all lines)
- Dokument
- Schedule base rates and the station cost index
- ERP-s
- Bill of Quantities
Price and bill
Ülesanne 4 · 30 min
Jooksev arve 1 ERP-s
- Sinu tulemus
- RA Bill 1 (the first part payment) in five lines, the share billed and the balance
- Dokument
- Contract: tendered amount and Schedule 'F'
- ERP-s
- Contracts
Get paid
Ülesanne 5 · 30 min
Mahaarvamised: tagatisdeposiit, heaolulõiv, GST
- Sinu tulemus
- The amount the institute pays
- Dokument
- Passed RA Bill 1 and the tax position
- ERP-s
- Contracts
From one wall to one payment
Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.
Sinine on see, mida ülesanne lisab; hall tuleb varasemast.
Lühidalt. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.