IS 1200-ийн дагуу хэмжилт ба нэхэмжлэл (Энэтхэг)

You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.

1-р даалгаврыг эхлэх

The RCC frame of a three-storey teaching block with bamboo scaffolding and green safety net, workers on the floor slabs, two women carrying head pans of mortar, and heaps of sand and aggregate in front.Зохиомол төсөл
Academic Block B, Sonapada InstituteRCC frame up, brickwork and plaster under way
Building
Ground plus two storey teaching block of a central institute
Contract
CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
Currency
Rupees, tendered rates inclusive of GST
ERP дээрх ажил
Даалгавар: 5, ойролцоогоор 2 цаг 45 мин

Хэн хэнд юу дамжуулдаг

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Танд ирдэг

  • Project ManagerYour firm, your side
    • Wall CW1 and its opening sizesДаалгавар 1
    • The tender percentage the company quotedДаалгавар 3
  • Engineer-in-ChargeInstitute Engineering Wing
    • Cost index notified for the stationДаалгавар 3
    • RA Bill 1, passed for paymentДаалгавар 5
ТаBilling engineer, your firm

Танаас гардаг

    • Brickwork measured to IS 1200Даалгавар 1
    • Plaster measured to IS 1200Даалгавар 2
    • RA Bill 1 and what is left to billДаалгавар 4
    Engineer-in-ChargeChecks measurements and bills
    • Recoveries and the amount payableДаалгавар 5
    Accounts officerInstitute, pays the bill

Төслөөр явах таны зам

Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.

  1. Measure the wall

    Даалгавар 1 · 35 мин

    Тоосгон өрлөгийг хэмжих: ямар нүхийг хасах вэ

    Үр дүн
    Brickwork volume of wall CW1 on line 2.3
    Баримт бичиг
    Elevation of CW1 with seven openings
    ERP дээр
    Bill of Quantities
  2. Measure the wall

    Даалгавар 2 · 35 мин

    Нэг ханан дээрх шавардлага: нэг биш, гурван босго

    Үр дүн
    Plaster area of the same wall on line 3.1
    Баримт бичиг
    The same elevation, plaster on both faces
    ERP дээр
    Bill of Quantities
  3. Price and bill

    Даалгавар 3 · 35 мин

    Хураангуйг тарифжуулах: суурь үнэлгээ, зардлын индекс, тендерийн хувь

    Үр дүн
    Gross value of the abstract (the priced summary of all lines)
    Баримт бичиг
    Schedule base rates and the station cost index
    ERP дээр
    Bill of Quantities
  4. Price and bill

    Даалгавар 4 · 30 мин

    ERP доторх 1-р явцын тооцоо (running account bill)

    Үр дүн
    RA Bill 1 (the first part payment) in five lines, the share billed and the balance
    Баримт бичиг
    Contract: tendered amount and Schedule 'F'
    ERP дээр
    Contracts
  5. Get paid

    Даалгавар 5 · 30 мин

    Суутгал: баталгаа хадгаламж, нийгмийн хамгааллын хураамж, GST

    Үр дүн
    The amount the institute pays
    Баримт бичиг
    Passed RA Bill 1 and the tax position
    ERP дээр
    Contracts

From one wall to one payment

Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.

Brickwork, m³
Даалгавар 1Brickwork by volumeOne face of the wall less the openings over 0.1 m², times the thickness, less the concrete (RCC) lintels over the openings.
Plaster, m²Brickwork, m³
Даалгавар 2Plaster by areaBoth faces, openings deducted by size band, reveals added only for the largest.
Tender %Cost indexAbstract at base rates
Даалгавар 3Base rates, then two additionsSchedule base rates on every line. The station cost index, the percentage for this location, on the base total; the tender percentage on the indexed total.
Gross of RA Bill 1
Даалгавар 4The same money as a billFive lines in the claim. The gross is measured against the tendered amount, not the estimate.
Cess, GST TDSSecurity depositPaid to the contractor
Даалгавар 5What reaches the bankSecurity deposit off the gross. The labour welfare cess and the GST tax deducted at source (TDS) come off the value without GST.

Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.

Товчхондоо. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.