You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.
Зохиомол төсөл- Building
- Ground plus two storey teaching block of a central institute
- Contract
- CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
- Currency
- Rupees, tendered rates inclusive of GST
- ERP дээрх ажил
- Даалгавар: 5, ойролцоогоор 2 цаг 45 мин
Хэн хэнд юу дамжуулдаг
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Танд ирдэг
- Project ManagerYour firm, your side
- Wall CW1 and its opening sizesДаалгавар 1
- The tender percentage the company quotedДаалгавар 3
- Engineer-in-ChargeInstitute Engineering Wing
- Cost index notified for the stationДаалгавар 3
- RA Bill 1, passed for paymentДаалгавар 5
Танаас гардаг
- Brickwork measured to IS 1200Даалгавар 1
- Plaster measured to IS 1200Даалгавар 2
- RA Bill 1 and what is left to billДаалгавар 4
- Recoveries and the amount payableДаалгавар 5
Төслөөр явах таны зам
Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.
Measure the wall
Даалгавар 1 · 35 мин
Тоосгон өрлөгийг хэмжих: ямар нүхийг хасах вэ
- Үр дүн
- Brickwork volume of wall CW1 on line 2.3
- Баримт бичиг
- Elevation of CW1 with seven openings
- ERP дээр
- Bill of Quantities
Measure the wall
Даалгавар 2 · 35 мин
Нэг ханан дээрх шавардлага: нэг биш, гурван босго
- Үр дүн
- Plaster area of the same wall on line 3.1
- Баримт бичиг
- The same elevation, plaster on both faces
- ERP дээр
- Bill of Quantities
Price and bill
Даалгавар 3 · 35 мин
Хураангуйг тарифжуулах: суурь үнэлгээ, зардлын индекс, тендерийн хувь
- Үр дүн
- Gross value of the abstract (the priced summary of all lines)
- Баримт бичиг
- Schedule base rates and the station cost index
- ERP дээр
- Bill of Quantities
Price and bill
Даалгавар 4 · 30 мин
ERP доторх 1-р явцын тооцоо (running account bill)
- Үр дүн
- RA Bill 1 (the first part payment) in five lines, the share billed and the balance
- Баримт бичиг
- Contract: tendered amount and Schedule 'F'
- ERP дээр
- Contracts
Get paid
Даалгавар 5 · 30 мин
Суутгал: баталгаа хадгаламж, нийгмийн хамгааллын хураамж, GST
- Үр дүн
- The amount the institute pays
- Баримт бичиг
- Passed RA Bill 1 and the tax position
- ERP дээр
- Contracts
From one wall to one payment
Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.
Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.
Товчхондоо. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.