Introduktion til kurset · 3 min
Opmåling efter IS 1200 og fakturering (Indien)
You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.
Fiktivt projekt- Building
- Ground plus two storey teaching block of a central institute
- Contract
- CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
- Currency
- Rupees, tendered rates inclusive of GST
- Arbejde i ERP
- 5 opgaver, cirka 2 t 45 min
Hvem giver hvad til hvem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer til dig
- Project ManagerYour firm, your side
- Wall CW1 and its opening sizesOpgave 1
- The tender percentage the company quotedOpgave 3
- Engineer-in-ChargeInstitute Engineering Wing
- Cost index notified for the stationOpgave 3
- RA Bill 1, passed for paymentOpgave 5
Går fra dig
- Brickwork measured to IS 1200Opgave 1
- Plaster measured to IS 1200Opgave 2
- RA Bill 1 and what is left to billOpgave 4
- Recoveries and the amount payableOpgave 5
Din vej gennem sagen
Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.
Measure the wall
Opgave 1 · 35 min
Opmål murværket: hvilke åbninger trækkes fra
- Du leverer
- Brickwork volume of wall CW1 on line 2.3
- Dokument
- Elevation of CW1 with seven openings
- I ERP
- Bill of Quantities
Measure the wall
Opgave 2 · 35 min
Puds på samme væg: tre grænseværdier, ikke én
- Du leverer
- Plaster area of the same wall on line 3.1
- Dokument
- The same elevation, plaster on both faces
- I ERP
- Bill of Quantities
Price and bill
Opgave 3 · 35 min
Prissæt mængdeopgørelsen: grundpriser, omkostningsindeks, tilbudsprocent
- Du leverer
- Gross value of the abstract (the priced summary of all lines)
- Dokument
- Schedule base rates and the station cost index
- I ERP
- Bill of Quantities
Price and bill
Opgave 4 · 30 min
A conto-regning 1 i ERP'et
- Du leverer
- RA Bill 1 (the first part payment) in five lines, the share billed and the balance
- Dokument
- Contract: tendered amount and Schedule 'F'
- I ERP
- Contracts
Get paid
Opgave 5 · 30 min
Fradrag: sikkerhedsstillelse, velfærdsafgift, GST
- Du leverer
- The amount the institute pays
- Dokument
- Passed RA Bill 1 and the tax position
- I ERP
- Contracts
From one wall to one payment
Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.
Blå er det, opgaven tilføjer; grå er overført fra før.
Kort sagt. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.