Inleiding tot de cursus · 3 min

Opmeten volgens IS 1200 en factureren (India)

You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.

Start opdracht 1

The RCC frame of a three-storey teaching block with bamboo scaffolding and green safety net, workers on the floor slabs, two women carrying head pans of mortar, and heaps of sand and aggregate in front.Fictief project
Academic Block B, Sonapada InstituteRCC frame up, brickwork and plaster under way
Building
Ground plus two storey teaching block of a central institute
Contract
CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
Currency
Rupees, tendered rates inclusive of GST
Werk in de ERP
5 opdrachten, ongeveer 2 u 45 min

Wie geeft wat aan wie

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Komt bij u

  • Project ManagerYour firm, your side
    • Wall CW1 and its opening sizesOpdracht 1
    • The tender percentage the company quotedOpdracht 3
  • Engineer-in-ChargeInstitute Engineering Wing
    • Cost index notified for the stationOpdracht 3
    • RA Bill 1, passed for paymentOpdracht 5
UBilling engineer, your firm

Gaat van u uit

    • Brickwork measured to IS 1200Opdracht 1
    • Plaster measured to IS 1200Opdracht 2
    • RA Bill 1 and what is left to billOpdracht 4
    Engineer-in-ChargeChecks measurements and bills
    • Recoveries and the amount payableOpdracht 5
    Accounts officerInstitute, pays the bill

Uw route door het project

Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.

  1. Measure the wall

    Opdracht 1 · 35 min

    Het metselwerk meten: welke openingen vallen weg

    U levert
    Brickwork volume of wall CW1 on line 2.3
    Document
    Elevation of CW1 with seven openings
    In de ERP
    Bill of Quantities
  2. Measure the wall

    Opdracht 2 · 35 min

    Pleisterwerk op dezelfde wand: drie drempels, niet één

    U levert
    Plaster area of the same wall on line 3.1
    Document
    The same elevation, plaster on both faces
    In de ERP
    Bill of Quantities
  3. Price and bill

    Opdracht 3 · 35 min

    Het abstract prijzen: basistarieven, kostenindex, tenderpercentage

    U levert
    Gross value of the abstract (the priced summary of all lines)
    Document
    Schedule base rates and the station cost index
    In de ERP
    Bill of Quantities
  4. Price and bill

    Opdracht 4 · 30 min

    Termijnstaat 1 in het ERP

    U levert
    RA Bill 1 (the first part payment) in five lines, the share billed and the balance
    Document
    Contract: tendered amount and Schedule 'F'
    In de ERP
    Contracts
  5. Get paid

    Opdracht 5 · 30 min

    Inhoudingen: waarborgsom, welzijnsheffing, GST

    U levert
    The amount the institute pays
    Document
    Passed RA Bill 1 and the tax position
    In de ERP
    Contracts

From one wall to one payment

Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.

Brickwork, m³
Opdracht 1Brickwork by volumeOne face of the wall less the openings over 0.1 m², times the thickness, less the concrete (RCC) lintels over the openings.
Plaster, m²Brickwork, m³
Opdracht 2Plaster by areaBoth faces, openings deducted by size band, reveals added only for the largest.
Tender %Cost indexAbstract at base rates
Opdracht 3Base rates, then two additionsSchedule base rates on every line. The station cost index, the percentage for this location, on the base total; the tender percentage on the indexed total.
Gross of RA Bill 1
Opdracht 4The same money as a billFive lines in the claim. The gross is measured against the tendered amount, not the estimate.
Cess, GST TDSSecurity depositPaid to the contractor
Opdracht 5What reaches the bankSecurity deposit off the gross. The labour welfare cess and the GST tax deducted at source (TDS) come off the value without GST.

Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.

Kort gezegd. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.