Inleiding tot de cursus · 3 min
Opmeten volgens IS 1200 en factureren (India)
You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.
Fictief project- Building
- Ground plus two storey teaching block of a central institute
- Contract
- CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
- Currency
- Rupees, tendered rates inclusive of GST
- Werk in de ERP
- 5 opdrachten, ongeveer 2 u 45 min
Wie geeft wat aan wie
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Komt bij u
- Project ManagerYour firm, your side
- Wall CW1 and its opening sizesOpdracht 1
- The tender percentage the company quotedOpdracht 3
- Engineer-in-ChargeInstitute Engineering Wing
- Cost index notified for the stationOpdracht 3
- RA Bill 1, passed for paymentOpdracht 5
Gaat van u uit
- Brickwork measured to IS 1200Opdracht 1
- Plaster measured to IS 1200Opdracht 2
- RA Bill 1 and what is left to billOpdracht 4
- Recoveries and the amount payableOpdracht 5
Uw route door het project
Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.
Measure the wall
Opdracht 1 · 35 min
Het metselwerk meten: welke openingen vallen weg
- U levert
- Brickwork volume of wall CW1 on line 2.3
- Document
- Elevation of CW1 with seven openings
- In de ERP
- Bill of Quantities
Measure the wall
Opdracht 2 · 35 min
Pleisterwerk op dezelfde wand: drie drempels, niet één
- U levert
- Plaster area of the same wall on line 3.1
- Document
- The same elevation, plaster on both faces
- In de ERP
- Bill of Quantities
Price and bill
Opdracht 3 · 35 min
Het abstract prijzen: basistarieven, kostenindex, tenderpercentage
- U levert
- Gross value of the abstract (the priced summary of all lines)
- Document
- Schedule base rates and the station cost index
- In de ERP
- Bill of Quantities
Price and bill
Opdracht 4 · 30 min
Termijnstaat 1 in het ERP
- U levert
- RA Bill 1 (the first part payment) in five lines, the share billed and the balance
- Document
- Contract: tendered amount and Schedule 'F'
- In de ERP
- Contracts
Get paid
Opdracht 5 · 30 min
Inhoudingen: waarborgsom, welzijnsheffing, GST
- U levert
- The amount the institute pays
- Document
- Passed RA Bill 1 and the tax position
- In de ERP
- Contracts
From one wall to one payment
Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.
Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.
Kort gezegd. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.