Uvod u tečaj · 3 min
Mjerenje prema IS 1200 i obračun (Indija)
You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.
Izmišljeni projekt- Building
- Ground plus two storey teaching block of a central institute
- Contract
- CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
- Currency
- Rupees, tendered rates inclusive of GST
- Rad u ERP-u
- Zadataka: 5, oko 2 h 45 min
Tko kome što predaje
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dolazi vama
- Project ManagerYour firm, your side
- Wall CW1 and its opening sizesZadatak 1
- The tender percentage the company quotedZadatak 3
- Engineer-in-ChargeInstitute Engineering Wing
- Cost index notified for the stationZadatak 3
- RA Bill 1, passed for paymentZadatak 5
Odlazi od vas
- Brickwork measured to IS 1200Zadatak 1
- Plaster measured to IS 1200Zadatak 2
- RA Bill 1 and what is left to billZadatak 4
- Recoveries and the amount payableZadatak 5
Vaš put kroz projekt
Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.
Measure the wall
Zadatak 1 · 35 min
Mjerenje zidarskih radova: koji se otvori odbijaju
- Vaš rezultat
- Brickwork volume of wall CW1 on line 2.3
- Dokument
- Elevation of CW1 with seven openings
- U ERP-u
- Bill of Quantities
Measure the wall
Zadatak 2 · 35 min
Žbuka na istom zidu: tri praga, ne jedan
- Vaš rezultat
- Plaster area of the same wall on line 3.1
- Dokument
- The same elevation, plaster on both faces
- U ERP-u
- Bill of Quantities
Price and bill
Zadatak 3 · 35 min
Odredi cijene troškovnika: osnovne cijene, troškovni indeks, postotak ponude
- Vaš rezultat
- Gross value of the abstract (the priced summary of all lines)
- Dokument
- Schedule base rates and the station cost index
- U ERP-u
- Bill of Quantities
Price and bill
Zadatak 4 · 30 min
Privremeni obračunski račun 1 u ERP-u
- Vaš rezultat
- RA Bill 1 (the first part payment) in five lines, the share billed and the balance
- Dokument
- Contract: tendered amount and Schedule 'F'
- U ERP-u
- Contracts
Get paid
Zadatak 5 · 30 min
Odbici: jamčevni depozit, cess za socijalnu skrb, GST
- Vaš rezultat
- The amount the institute pays
- Dokument
- Passed RA Bill 1 and the tax position
- U ERP-u
- Contracts
From one wall to one payment
Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.
Plavo je ono što zadatak dodaje; sivo se prenosi od prije.
Ukratko. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.