معرفی دوره · 3 دقیقه

اندازه‌گیری طبق IS 1200 و صورت‌حساب (هند)

You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.

شروع تکلیف 1

The RCC frame of a three-storey teaching block with bamboo scaffolding and green safety net, workers on the floor slabs, two women carrying head pans of mortar, and heaps of sand and aggregate in front.پروژهٔ خیالی
Academic Block B, Sonapada InstituteRCC frame up, brickwork and plaster under way
Building
Ground plus two storey teaching block of a central institute
Contract
CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
Currency
Rupees, tendered rates inclusive of GST
کار در ERP
5 تکلیف، حدود 2 ساعت 45 دقیقه

چه کسی چه چیزی به چه کسی می‌دهد

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

به شما می‌رسد

  • Project ManagerYour firm, your side
    • Wall CW1 and its opening sizesتکلیف 1
    • The tender percentage the company quotedتکلیف 3
  • Engineer-in-ChargeInstitute Engineering Wing
    • Cost index notified for the stationتکلیف 3
    • RA Bill 1, passed for paymentتکلیف 5
شماBilling engineer, your firm

از شما می‌رود

    • Brickwork measured to IS 1200تکلیف 1
    • Plaster measured to IS 1200تکلیف 2
    • RA Bill 1 and what is left to billتکلیف 4
    Engineer-in-ChargeChecks measurements and bills
    • Recoveries and the amount payableتکلیف 5
    Accounts officerInstitute, pays the bill

مسیر شما در پروژه

Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.

  1. Measure the wall

    تکلیف 1 · 35 دقیقه

    اندازه‌گیری آجرکاری: کدام بازشوها کسر می‌شوند

    خروجی شما
    Brickwork volume of wall CW1 on line 2.3
    سند
    Elevation of CW1 with seven openings
    در ERP
    Bill of Quantities
  2. Measure the wall

    تکلیف 2 · 35 دقیقه

    اندود روی همان دیوار: سه آستانه، نه یکی

    خروجی شما
    Plaster area of the same wall on line 3.1
    سند
    The same elevation, plaster on both faces
    در ERP
    Bill of Quantities
  3. Price and bill

    تکلیف 3 · 35 دقیقه

    قیمت‌گذاری صورت‌ریز: نرخ‌های پایه، شاخص هزینه، درصد پیشنهاد مناقصه

    خروجی شما
    Gross value of the abstract (the priced summary of all lines)
    سند
    Schedule base rates and the station cost index
    در ERP
    Bill of Quantities
  4. Price and bill

    تکلیف 4 · 30 دقیقه

    صورت‌حساب حساب جاری شمارهٔ 1 در ERP

    خروجی شما
    RA Bill 1 (the first part payment) in five lines, the share billed and the balance
    سند
    Contract: tendered amount and Schedule 'F'
    در ERP
    Contracts
  5. Get paid

    تکلیف 5 · 30 دقیقه

    کسورات: سپردهٔ تضمین، عوارض رفاه (cess)، GST

    خروجی شما
    The amount the institute pays
    سند
    Passed RA Bill 1 and the tax position
    در ERP
    Contracts

From one wall to one payment

Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.

Brickwork, m³
تکلیف 1Brickwork by volumeOne face of the wall less the openings over 0.1 m², times the thickness, less the concrete (RCC) lintels over the openings.
Plaster, m²Brickwork, m³
تکلیف 2Plaster by areaBoth faces, openings deducted by size band, reveals added only for the largest.
Tender %Cost indexAbstract at base rates
تکلیف 3Base rates, then two additionsSchedule base rates on every line. The station cost index, the percentage for this location, on the base total; the tender percentage on the indexed total.
Gross of RA Bill 1
تکلیف 4The same money as a billFive lines in the claim. The gross is measured against the tendered amount, not the estimate.
Cess, GST TDSSecurity depositPaid to the contractor
تکلیف 5What reaches the bankSecurity deposit off the gross. The labour welfare cess and the GST tax deducted at source (TDS) come off the value without GST.

آبی چیزی است که تکلیف اضافه می‌کند؛ خاکستری از مرحلهٔ قبل آمده است.

به‌طور خلاصه. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.