Kurssin johdanto · 3 min

Mittaus IS 1200 -standardin mukaan ja laskutus (Intia)

You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.

Aloita tehtävä 1

The RCC frame of a three-storey teaching block with bamboo scaffolding and green safety net, workers on the floor slabs, two women carrying head pans of mortar, and heaps of sand and aggregate in front.Kuvitteellinen hanke
Academic Block B, Sonapada InstituteRCC frame up, brickwork and plaster under way
Building
Ground plus two storey teaching block of a central institute
Contract
CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
Currency
Rupees, tendered rates inclusive of GST
Työ ERP:ssä
Tehtäviä 5, noin 2 t 45 min

Kuka antaa mitä kenelle

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Tulee sinulle

  • Project ManagerYour firm, your side
    • Wall CW1 and its opening sizesTehtävä 1
    • The tender percentage the company quotedTehtävä 3
  • Engineer-in-ChargeInstitute Engineering Wing
    • Cost index notified for the stationTehtävä 3
    • RA Bill 1, passed for paymentTehtävä 5
SinäBilling engineer, your firm

Lähtee sinulta

    • Brickwork measured to IS 1200Tehtävä 1
    • Plaster measured to IS 1200Tehtävä 2
    • RA Bill 1 and what is left to billTehtävä 4
    Engineer-in-ChargeChecks measurements and bills
    • Recoveries and the amount payableTehtävä 5
    Accounts officerInstitute, pays the bill

Reittisi hankkeen läpi

Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.

  1. Measure the wall

    Tehtävä 1 · 35 min

    Mittaa tiilimuuraus: mitkä aukot vähennetään

    Tuotat
    Brickwork volume of wall CW1 on line 2.3
    Asiakirja
    Elevation of CW1 with seven openings
    ERP:ssä
    Bill of Quantities
  2. Measure the wall

    Tehtävä 2 · 35 min

    Rappaus samalla seinällä: kolme kynnystä, ei yksi

    Tuotat
    Plaster area of the same wall on line 3.1
    Asiakirja
    The same elevation, plaster on both faces
    ERP:ssä
    Bill of Quantities
  3. Price and bill

    Tehtävä 3 · 35 min

    Hinnoittele yhteenveto: perushinnat, kustannusindeksi, tarjousprosentti

    Tuotat
    Gross value of the abstract (the priced summary of all lines)
    Asiakirja
    Schedule base rates and the station cost index
    ERP:ssä
    Bill of Quantities
  4. Price and bill

    Tehtävä 4 · 30 min

    Osalasku 1 ERP:ssä

    Tuotat
    RA Bill 1 (the first part payment) in five lines, the share billed and the balance
    Asiakirja
    Contract: tendered amount and Schedule 'F'
    ERP:ssä
    Contracts
  5. Get paid

    Tehtävä 5 · 30 min

    Vähennykset: vakuustalletus, hyvinvointimaksu, GST

    Tuotat
    The amount the institute pays
    Asiakirja
    Passed RA Bill 1 and the tax position
    ERP:ssä
    Contracts

From one wall to one payment

Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.

Brickwork, m³
Tehtävä 1Brickwork by volumeOne face of the wall less the openings over 0.1 m², times the thickness, less the concrete (RCC) lintels over the openings.
Plaster, m²Brickwork, m³
Tehtävä 2Plaster by areaBoth faces, openings deducted by size band, reveals added only for the largest.
Tender %Cost indexAbstract at base rates
Tehtävä 3Base rates, then two additionsSchedule base rates on every line. The station cost index, the percentage for this location, on the base total; the tender percentage on the indexed total.
Gross of RA Bill 1
Tehtävä 4The same money as a billFive lines in the claim. The gross is measured against the tendered amount, not the estimate.
Cess, GST TDSSecurity depositPaid to the contractor
Tehtävä 5What reaches the bankSecurity deposit off the gross. The labour welfare cess and the GST tax deducted at source (TDS) come off the value without GST.

Sininen on se, mitä tehtävä lisää; harmaa tulee aiemmasta.

Lyhyesti. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.