Úvod do kurzu · 3 min

Měření podle IS 1200 a fakturace (Indie)

You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.

Začít úlohu 1

The RCC frame of a three-storey teaching block with bamboo scaffolding and green safety net, workers on the floor slabs, two women carrying head pans of mortar, and heaps of sand and aggregate in front.Smyšlený projekt
Academic Block B, Sonapada InstituteRCC frame up, brickwork and plaster under way
Building
Ground plus two storey teaching block of a central institute
Contract
CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
Currency
Rupees, tendered rates inclusive of GST
Práce v ERP
Úlohy: 5, asi 2 h 45 min

Kdo komu co předává

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Přichází k vám

  • Project ManagerYour firm, your side
    • Wall CW1 and its opening sizesÚloha 1
    • The tender percentage the company quotedÚloha 3
  • Engineer-in-ChargeInstitute Engineering Wing
    • Cost index notified for the stationÚloha 3
    • RA Bill 1, passed for paymentÚloha 5
VyBilling engineer, your firm

Odchází od vás

    • Brickwork measured to IS 1200Úloha 1
    • Plaster measured to IS 1200Úloha 2
    • RA Bill 1 and what is left to billÚloha 4
    Engineer-in-ChargeChecks measurements and bills
    • Recoveries and the amount payableÚloha 5
    Accounts officerInstitute, pays the bill

Vaše cesta zakázkou

Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.

  1. Measure the wall

    Úloha 1 · 35 min

    Změřte zdivo: které otvory se odečítají

    Výstup
    Brickwork volume of wall CW1 on line 2.3
    Dokument
    Elevation of CW1 with seven openings
    V ERP
    Bill of Quantities
  2. Measure the wall

    Úloha 2 · 35 min

    Omítka na téže stěně: tři prahy, ne jeden

    Výstup
    Plaster area of the same wall on line 3.1
    Dokument
    The same elevation, plaster on both faces
    V ERP
    Bill of Quantities
  3. Price and bill

    Úloha 3 · 35 min

    Oceňte abstract: základní sazby, cenový index, nabídkové procento

    Výstup
    Gross value of the abstract (the priced summary of all lines)
    Dokument
    Schedule base rates and the station cost index
    V ERP
    Bill of Quantities
  4. Price and bill

    Úloha 4 · 30 min

    Postupová faktura RA Bill 1 v ERP

    Výstup
    RA Bill 1 (the first part payment) in five lines, the share billed and the balance
    Dokument
    Contract: tendered amount and Schedule 'F'
    V ERP
    Contracts
  5. Get paid

    Úloha 5 · 30 min

    Srážky: jistota, sociální odvod (welfare cess), GST

    Výstup
    The amount the institute pays
    Dokument
    Passed RA Bill 1 and the tax position
    V ERP
    Contracts

From one wall to one payment

Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.

Brickwork, m³
Úloha 1Brickwork by volumeOne face of the wall less the openings over 0.1 m², times the thickness, less the concrete (RCC) lintels over the openings.
Plaster, m²Brickwork, m³
Úloha 2Plaster by areaBoth faces, openings deducted by size band, reveals added only for the largest.
Tender %Cost indexAbstract at base rates
Úloha 3Base rates, then two additionsSchedule base rates on every line. The station cost index, the percentage for this location, on the base total; the tender percentage on the indexed total.
Gross of RA Bill 1
Úloha 4The same money as a billFive lines in the claim. The gross is measured against the tendered amount, not the estimate.
Cess, GST TDSSecurity depositPaid to the contractor
Úloha 5What reaches the bankSecurity deposit off the gross. The labour welfare cess and the GST tax deducted at source (TDS) come off the value without GST.

Modře je to, co úloha přidává; šedě to, co se přenáší z dřívějška.

Stručně. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.