Panimula ng kurso · 3 min
Sukat ayon sa IS 1200 at pagsingil (India)
You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.
Kathang-isip na proyekto- Building
- Ground plus two storey teaching block of a central institute
- Contract
- CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
- Currency
- Rupees, tendered rates inclusive of GST
- Trabaho sa ERP
- 5 gawain, mga 2 oras 45 min
Sino ang nagbibigay ng ano kanino
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dumarating sa iyo
- Project ManagerYour firm, your side
- Wall CW1 and its opening sizesGawain 1
- The tender percentage the company quotedGawain 3
- Engineer-in-ChargeInstitute Engineering Wing
- Cost index notified for the stationGawain 3
- RA Bill 1, passed for paymentGawain 5
Lumalabas sa iyo
- Brickwork measured to IS 1200Gawain 1
- Plaster measured to IS 1200Gawain 2
- RA Bill 1 and what is left to billGawain 4
- Recoveries and the amount payableGawain 5
Ang ruta mo sa proyekto
Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.
Measure the wall
Gawain 1 · 35 min
Sukatin ang brickwork: aling mga bukana ang ibinabawas
- Ang gagawin mo
- Brickwork volume of wall CW1 on line 2.3
- Dokumento
- Elevation of CW1 with seven openings
- Sa ERP
- Bill of Quantities
Measure the wall
Gawain 2 · 35 min
Plaster sa parehong dingding: tatlong threshold, hindi isa
- Ang gagawin mo
- Plaster area of the same wall on line 3.1
- Dokumento
- The same elevation, plaster on both faces
- Sa ERP
- Bill of Quantities
Price and bill
Gawain 3 · 35 min
Presyuhan ang abstract: base rates, cost index, tender percentage
- Ang gagawin mo
- Gross value of the abstract (the priced summary of all lines)
- Dokumento
- Schedule base rates and the station cost index
- Sa ERP
- Bill of Quantities
Price and bill
Gawain 4 · 30 min
Running account bill 1 sa ERP
- Ang gagawin mo
- RA Bill 1 (the first part payment) in five lines, the share billed and the balance
- Dokumento
- Contract: tendered amount and Schedule 'F'
- Sa ERP
- Contracts
Get paid
Gawain 5 · 30 min
Mga Recovery: security deposit, welfare cess, GST
- Ang gagawin mo
- The amount the institute pays
- Dokumento
- Passed RA Bill 1 and the tax position
- Sa ERP
- Contracts
From one wall to one payment
Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.
Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.
Sa madaling salita. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.