Sukat ayon sa IS 1200 at pagsingil (India)

You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.

Simulan ang gawain 1

The RCC frame of a three-storey teaching block with bamboo scaffolding and green safety net, workers on the floor slabs, two women carrying head pans of mortar, and heaps of sand and aggregate in front.Kathang-isip na proyekto
Academic Block B, Sonapada InstituteRCC frame up, brickwork and plaster under way
Building
Ground plus two storey teaching block of a central institute
Contract
CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
Currency
Rupees, tendered rates inclusive of GST
Trabaho sa ERP
5 gawain, mga 2 oras 45 min

Sino ang nagbibigay ng ano kanino

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dumarating sa iyo

  • Project ManagerYour firm, your side
    • Wall CW1 and its opening sizesGawain 1
    • The tender percentage the company quotedGawain 3
  • Engineer-in-ChargeInstitute Engineering Wing
    • Cost index notified for the stationGawain 3
    • RA Bill 1, passed for paymentGawain 5
IkawBilling engineer, your firm

Lumalabas sa iyo

    • Brickwork measured to IS 1200Gawain 1
    • Plaster measured to IS 1200Gawain 2
    • RA Bill 1 and what is left to billGawain 4
    Engineer-in-ChargeChecks measurements and bills
    • Recoveries and the amount payableGawain 5
    Accounts officerInstitute, pays the bill

Ang ruta mo sa proyekto

Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.

  1. Measure the wall

    Gawain 1 · 35 min

    Sukatin ang brickwork: aling mga bukana ang ibinabawas

    Ang gagawin mo
    Brickwork volume of wall CW1 on line 2.3
    Dokumento
    Elevation of CW1 with seven openings
    Sa ERP
    Bill of Quantities
  2. Measure the wall

    Gawain 2 · 35 min

    Plaster sa parehong dingding: tatlong threshold, hindi isa

    Ang gagawin mo
    Plaster area of the same wall on line 3.1
    Dokumento
    The same elevation, plaster on both faces
    Sa ERP
    Bill of Quantities
  3. Price and bill

    Gawain 3 · 35 min

    Presyuhan ang abstract: base rates, cost index, tender percentage

    Ang gagawin mo
    Gross value of the abstract (the priced summary of all lines)
    Dokumento
    Schedule base rates and the station cost index
    Sa ERP
    Bill of Quantities
  4. Price and bill

    Gawain 4 · 30 min

    Running account bill 1 sa ERP

    Ang gagawin mo
    RA Bill 1 (the first part payment) in five lines, the share billed and the balance
    Dokumento
    Contract: tendered amount and Schedule 'F'
    Sa ERP
    Contracts
  5. Get paid

    Gawain 5 · 30 min

    Mga Recovery: security deposit, welfare cess, GST

    Ang gagawin mo
    The amount the institute pays
    Dokumento
    Passed RA Bill 1 and the tax position
    Sa ERP
    Contracts

From one wall to one payment

Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.

Brickwork, m³
Gawain 1Brickwork by volumeOne face of the wall less the openings over 0.1 m², times the thickness, less the concrete (RCC) lintels over the openings.
Plaster, m²Brickwork, m³
Gawain 2Plaster by areaBoth faces, openings deducted by size band, reveals added only for the largest.
Tender %Cost indexAbstract at base rates
Gawain 3Base rates, then two additionsSchedule base rates on every line. The station cost index, the percentage for this location, on the base total; the tender percentage on the indexed total.
Gross of RA Bill 1
Gawain 4The same money as a billFive lines in the claim. The gross is measured against the tendered amount, not the estimate.
Cess, GST TDSSecurity depositPaid to the contractor
Gawain 5What reaches the bankSecurity deposit off the gross. The labour welfare cess and the GST tax deducted at source (TDS) come off the value without GST.

Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.

Sa madaling salita. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.