מבוא לקורס · 3 דק׳

מדידה לפי IS 1200 וחיוב (הודו)

You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.

התחלת משימה 1

The RCC frame of a three-storey teaching block with bamboo scaffolding and green safety net, workers on the floor slabs, two women carrying head pans of mortar, and heaps of sand and aggregate in front.פרויקט בדיוני
Academic Block B, Sonapada InstituteRCC frame up, brickwork and plaster under way
Building
Ground plus two storey teaching block of a central institute
Contract
CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
Currency
Rupees, tendered rates inclusive of GST
עבודה ב-ERP
5 משימות, כ-2 ש׳ 45 דק׳

מי מעביר מה למי

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

מגיע אליכם

  • Project ManagerYour firm, your side
    • Wall CW1 and its opening sizesמשימה 1
    • The tender percentage the company quotedמשימה 3
  • Engineer-in-ChargeInstitute Engineering Wing
    • Cost index notified for the stationמשימה 3
    • RA Bill 1, passed for paymentמשימה 5
אתםBilling engineer, your firm

יוצא מכם

    • Brickwork measured to IS 1200משימה 1
    • Plaster measured to IS 1200משימה 2
    • RA Bill 1 and what is left to billמשימה 4
    Engineer-in-ChargeChecks measurements and bills
    • Recoveries and the amount payableמשימה 5
    Accounts officerInstitute, pays the bill

המסלול שלכם בפרויקט

Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.

  1. Measure the wall

    משימה 1 · 35 דק׳

    מדידת בניית הלבנים: אילו פתחים יוצאים מהחישוב

    התוצר שלכם
    Brickwork volume of wall CW1 on line 2.3
    מסמך
    Elevation of CW1 with seven openings
    ב-ERP
    Bill of Quantities
  2. Measure the wall

    משימה 2 · 35 דק׳

    טיח על אותו קיר: שלושה ספים, לא אחד

    התוצר שלכם
    Plaster area of the same wall on line 3.1
    מסמך
    The same elevation, plaster on both faces
    ב-ERP
    Bill of Quantities
  3. Price and bill

    משימה 3 · 35 דק׳

    תמחור תקציר הכמויות: תעריפי בסיס, מדד עלות, אחוז המכרז

    התוצר שלכם
    Gross value of the abstract (the priced summary of all lines)
    מסמך
    Schedule base rates and the station cost index
    ב-ERP
    Bill of Quantities
  4. Price and bill

    משימה 4 · 30 דק׳

    חשבון חלקי 1 (running account bill) ב-ERP

    התוצר שלכם
    RA Bill 1 (the first part payment) in five lines, the share billed and the balance
    מסמך
    Contract: tendered amount and Schedule 'F'
    ב-ERP
    Contracts
  5. Get paid

    משימה 5 · 30 דק׳

    ניכויים: פיקדון ערובה, היטל רווחה, GST

    התוצר שלכם
    The amount the institute pays
    מסמך
    Passed RA Bill 1 and the tax position
    ב-ERP
    Contracts

From one wall to one payment

Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.

Brickwork, m³
משימה 1Brickwork by volumeOne face of the wall less the openings over 0.1 m², times the thickness, less the concrete (RCC) lintels over the openings.
Plaster, m²Brickwork, m³
משימה 2Plaster by areaBoth faces, openings deducted by size band, reveals added only for the largest.
Tender %Cost indexAbstract at base rates
משימה 3Base rates, then two additionsSchedule base rates on every line. The station cost index, the percentage for this location, on the base total; the tender percentage on the indexed total.
Gross of RA Bill 1
משימה 4The same money as a billFive lines in the claim. The gross is measured against the tendered amount, not the estimate.
Cess, GST TDSSecurity depositPaid to the contractor
משימה 5What reaches the bankSecurity deposit off the gross. The labour welfare cess and the GST tax deducted at source (TDS) come off the value without GST.

בכחול מה שהמשימה מוסיפה; באפור מה שעבר מהשלב הקודם.

בקצרה. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.