Introduksjon til kurset · 3 min

Oppmåling etter IS 1200 og fakturering (India)

You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.

Start oppgave 1

The RCC frame of a three-storey teaching block with bamboo scaffolding and green safety net, workers on the floor slabs, two women carrying head pans of mortar, and heaps of sand and aggregate in front.Fiktivt prosjekt
Academic Block B, Sonapada InstituteRCC frame up, brickwork and plaster under way
Building
Ground plus two storey teaching block of a central institute
Contract
CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
Currency
Rupees, tendered rates inclusive of GST
Arbeid i ERP
5 oppgaver, omtrent 2 t 45 min

Hvem gir hva til hvem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer til deg

  • Project ManagerYour firm, your side
    • Wall CW1 and its opening sizesOppgave 1
    • The tender percentage the company quotedOppgave 3
  • Engineer-in-ChargeInstitute Engineering Wing
    • Cost index notified for the stationOppgave 3
    • RA Bill 1, passed for paymentOppgave 5
DuBilling engineer, your firm

Går fra deg

    • Brickwork measured to IS 1200Oppgave 1
    • Plaster measured to IS 1200Oppgave 2
    • RA Bill 1 and what is left to billOppgave 4
    Engineer-in-ChargeChecks measurements and bills
    • Recoveries and the amount payableOppgave 5
    Accounts officerInstitute, pays the bill

Din vei gjennom prosjektet

Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.

  1. Measure the wall

    Oppgave 1 · 35 min

    Mål murverket: hvilke åpninger trekkes fra

    Du leverer
    Brickwork volume of wall CW1 on line 2.3
    Dokument
    Elevation of CW1 with seven openings
    I ERP
    Bill of Quantities
  2. Measure the wall

    Oppgave 2 · 35 min

    Puss på samme vegg: tre terskler, ikke én

    Du leverer
    Plaster area of the same wall on line 3.1
    Dokument
    The same elevation, plaster on both faces
    I ERP
    Bill of Quantities
  3. Price and bill

    Oppgave 3 · 35 min

    Prissett sammendraget: grunnsatser, kostnadsindeks, tilbudsprosent

    Du leverer
    Gross value of the abstract (the priced summary of all lines)
    Dokument
    Schedule base rates and the station cost index
    I ERP
    Bill of Quantities
  4. Price and bill

    Oppgave 4 · 30 min

    Løpende avregning 1 i ERP-systemet

    Du leverer
    RA Bill 1 (the first part payment) in five lines, the share billed and the balance
    Dokument
    Contract: tendered amount and Schedule 'F'
    I ERP
    Contracts
  5. Get paid

    Oppgave 5 · 30 min

    Fratrekk: tilbakehold, velferdsavgift, GST

    Du leverer
    The amount the institute pays
    Dokument
    Passed RA Bill 1 and the tax position
    I ERP
    Contracts

From one wall to one payment

Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.

Brickwork, m³
Oppgave 1Brickwork by volumeOne face of the wall less the openings over 0.1 m², times the thickness, less the concrete (RCC) lintels over the openings.
Plaster, m²Brickwork, m³
Oppgave 2Plaster by areaBoth faces, openings deducted by size band, reveals added only for the largest.
Tender %Cost indexAbstract at base rates
Oppgave 3Base rates, then two additionsSchedule base rates on every line. The station cost index, the percentage for this location, on the base total; the tender percentage on the indexed total.
Gross of RA Bill 1
Oppgave 4The same money as a billFive lines in the claim. The gross is measured against the tendered amount, not the estimate.
Cess, GST TDSSecurity depositPaid to the contractor
Oppgave 5What reaches the bankSecurity deposit off the gross. The labour welfare cess and the GST tax deducted at source (TDS) come off the value without GST.

Blått er det oppgaven legger til; grått er overført fra før.

Kort sagt. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.