Introducere în curs · 3 min
Măsurare conform IS 1200 și facturare (India)
You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.
Proiect fictiv- Building
- Ground plus two storey teaching block of a central institute
- Contract
- CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
- Currency
- Rupees, tendered rates inclusive of GST
- Lucru în ERP
- 5 sarcini, circa 2 h 45 min
Cine ce predă cui
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Ajunge la tine
- Project ManagerYour firm, your side
- Wall CW1 and its opening sizesSarcina 1
- The tender percentage the company quotedSarcina 3
- Engineer-in-ChargeInstitute Engineering Wing
- Cost index notified for the stationSarcina 3
- RA Bill 1, passed for paymentSarcina 5
Pleacă de la tine
- Brickwork measured to IS 1200Sarcina 1
- Plaster measured to IS 1200Sarcina 2
- RA Bill 1 and what is left to billSarcina 4
- Recoveries and the amount payableSarcina 5
Traseul tău prin proiect
Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.
Measure the wall
Sarcina 1 · 35 min
Măsurarea zidăriei: care goluri se scad
- Produci
- Brickwork volume of wall CW1 on line 2.3
- Document
- Elevation of CW1 with seven openings
- În ERP
- Bill of Quantities
Measure the wall
Sarcina 2 · 35 min
Tencuiala pe același perete: trei praguri, nu unul singur
- Produci
- Plaster area of the same wall on line 3.1
- Document
- The same elevation, plaster on both faces
- În ERP
- Bill of Quantities
Price and bill
Sarcina 3 · 35 min
Stabilirea prețului recapitulației: tarife de bază, indice de cost, procent de ofertă
- Produci
- Gross value of the abstract (the priced summary of all lines)
- Document
- Schedule base rates and the station cost index
- În ERP
- Bill of Quantities
Price and bill
Sarcina 4 · 30 min
Factura de cont curent 1 în ERP
- Produci
- RA Bill 1 (the first part payment) in five lines, the share billed and the balance
- Document
- Contract: tendered amount and Schedule 'F'
- În ERP
- Contracts
Get paid
Sarcina 5 · 30 min
Rețineri: depozitul de garanție, taxa de asistență socială, GST
- Produci
- The amount the institute pays
- Document
- Passed RA Bill 1 and the tax position
- În ERP
- Contracts
From one wall to one payment
Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.
Albastru este ce adaugă sarcina; gri este ce vine de dinainte.
Pe scurt. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.