Introducere în curs · 3 min

Măsurare conform IS 1200 și facturare (India)

You are the billing engineer of the contractor building a teaching block for a central institute: you measure the work done and bill for it. In five tasks you measure one brick wall by the Indian standard IS 1200, price the bill at schedule rates, the government's published rates, raise the first running account (RA) bill, the monthly part payment, and work out what the institute actually pays after deductions.

Începe sarcina 1

The RCC frame of a three-storey teaching block with bamboo scaffolding and green safety net, workers on the floor slabs, two women carrying head pans of mortar, and heaps of sand and aggregate in front.Proiect fictiv
Academic Block B, Sonapada InstituteRCC frame up, brickwork and plaster under way
Building
Ground plus two storey teaching block of a central institute
Contract
CPWD General Conditions of Contract 2023; bidders quote one percentage above or below the schedule of rates
Currency
Rupees, tendered rates inclusive of GST
Lucru în ERP
5 sarcini, circa 2 h 45 min

Cine ce predă cui

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Ajunge la tine

  • Project ManagerYour firm, your side
    • Wall CW1 and its opening sizesSarcina 1
    • The tender percentage the company quotedSarcina 3
  • Engineer-in-ChargeInstitute Engineering Wing
    • Cost index notified for the stationSarcina 3
    • RA Bill 1, passed for paymentSarcina 5
TuBilling engineer, your firm

Pleacă de la tine

    • Brickwork measured to IS 1200Sarcina 1
    • Plaster measured to IS 1200Sarcina 2
    • RA Bill 1 and what is left to billSarcina 4
    Engineer-in-ChargeChecks measurements and bills
    • Recoveries and the amount payableSarcina 5
    Accounts officerInstitute, pays the bill

Traseul tău prin proiect

Two tasks measure, two price and bill, one gets the money in. Start with task 1: in the Bill of Quantities you measure the brickwork volume of wall CW1 for line 2.3.

  1. Measure the wall

    Sarcina 1 · 35 min

    Măsurarea zidăriei: care goluri se scad

    Produci
    Brickwork volume of wall CW1 on line 2.3
    Document
    Elevation of CW1 with seven openings
    În ERP
    Bill of Quantities
  2. Measure the wall

    Sarcina 2 · 35 min

    Tencuiala pe același perete: trei praguri, nu unul singur

    Produci
    Plaster area of the same wall on line 3.1
    Document
    The same elevation, plaster on both faces
    În ERP
    Bill of Quantities
  3. Price and bill

    Sarcina 3 · 35 min

    Stabilirea prețului recapitulației: tarife de bază, indice de cost, procent de ofertă

    Produci
    Gross value of the abstract (the priced summary of all lines)
    Document
    Schedule base rates and the station cost index
    În ERP
    Bill of Quantities
  4. Price and bill

    Sarcina 4 · 30 min

    Factura de cont curent 1 în ERP

    Produci
    RA Bill 1 (the first part payment) in five lines, the share billed and the balance
    Document
    Contract: tendered amount and Schedule 'F'
    În ERP
    Contracts
  5. Get paid

    Sarcina 5 · 30 min

    Rețineri: depozitul de garanție, taxa de asistență socială, GST

    Produci
    The amount the institute pays
    Document
    Passed RA Bill 1 and the tax position
    În ERP
    Contracts

From one wall to one payment

Each task adds one layer to the same money. The new layer is in colour; what it sits on is grey.

Brickwork, m³
Sarcina 1Brickwork by volumeOne face of the wall less the openings over 0.1 m², times the thickness, less the concrete (RCC) lintels over the openings.
Plaster, m²Brickwork, m³
Sarcina 2Plaster by areaBoth faces, openings deducted by size band, reveals added only for the largest.
Tender %Cost indexAbstract at base rates
Sarcina 3Base rates, then two additionsSchedule base rates on every line. The station cost index, the percentage for this location, on the base total; the tender percentage on the indexed total.
Gross of RA Bill 1
Sarcina 4The same money as a billFive lines in the claim. The gross is measured against the tendered amount, not the estimate.
Cess, GST TDSSecurity depositPaid to the contractor
Sarcina 5What reaches the bankSecurity deposit off the gross. The labour welfare cess and the GST tax deducted at source (TDS) come off the value without GST.

Albastru este ce adaugă sarcina; gri este ce vine de dinainte.

Pe scurt. Brick and plaster have different thresholds. Index first, tender percentage on top. Bill against the tendered amount. Deposit on the gross, cess and tax at source on the value without GST.