Въведение в курса · 3 мин
График на WIP: процент на завършеност и над/под фактуриране (САЩ)
You are the project accountant at a general contractor building a block of shops with apartments above. Each month the firm reports every open job on one line of its work-in-progress (WIP) schedule, which banks and bonding companies read. In four tasks you close October for this job: how complete it is, how much revenue it has earned, whether billing runs ahead of the work, and the loss the new forecast reveals.
Измислен проект- Building
- Three stories: retail on a concrete podium, two wood-frame apartment floors
- Contract
- AIA A101 stipulated sum (one fixed price) with A201 general conditions; revenue counted under ASC 606
- Period
- October 2026 month-end close
- Работа в ERP
- Задачи: 4, около 2 ч 10 мин
Кой какво предава на кого
Every arrow is a figure or a document that reaches your desk or leaves it, and the task where that happens.
Идва при вас
- Project managerYour firm
- Cost to completeЗадача 1
- ReforecastЗадача 4
- The ownerOwner
- Change orders, signed and unsignedЗадача 2
- SuperintendentYour firm
- Stairs delivered, not installedЗадача 3
Тръгва от вас
- CVR month 2026-10Задача 1
- Earned revenue and gross profitЗадача 2
- Over/under billingЗадача 3
- Loss provisionЗадача 4
Вашият път през проекта
Two tasks build the WIP line, one checks it against stored material and billing, one tests it against a loss. Start with task 1: from the job cost report you work out cost to date, the forecast final cost and the percent complete.
The WIP line
Задача 1 · 30 мин
Разходи до момента, оценка при завършване, процент на завършеност
- Вашият резултат
- Cost to date, estimate at completion, percent complete
- Документ
- Job cost report, October 2026
- В ERP
- Cost-Value Reconciliation
The WIP line
Задача 2 · 30 мин
Признати приходи и брутна печалба
- Вашият резултат
- Contract value, earned revenue and both gross profits
- Документ
- Contract sum and change orders CO-01 to CO-03
- В ERP
- Cost-Value Reconciliation, REV head
Billing check
Задача 3 · 35 мин
Немонтирани материали и над/подфактуриране
- Вашият резултат
- Revenue with the stairs at cost, and the billing position
- Документ
- AIA G702, pay application 9 (the monthly bill)
- В ERP
- Cost-Value Reconciliation, Edit cost head
Reforecast
Задача 4 · 35 мин
Проект на загуба: цялата загуба сега
- Вашият резултат
- The provision for anticipated loss (the whole expected loss, booked now)
- Документ
- Reforecast before the close
- В ERP
- Cost-Value Reconciliation, LOSS head
How cost turns into revenue on a WIP line
Each bar is one task, in the order the October close runs.
В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.
Накратко. Cost against cost for the percent. Stored material at cost, no margin. Gross billings against earned revenue. A loss goes in whole, the month you see it.