Курсқа кіріспе · 3 мин
WIP кестесі: аяқталу пайызы және артық/кем шот жазу (АҚШ)
You are the project accountant at a general contractor building a block of shops with apartments above. Each month the firm reports every open job on one line of its work-in-progress (WIP) schedule, which banks and bonding companies read. In four tasks you close October for this job: how complete it is, how much revenue it has earned, whether billing runs ahead of the work, and the loss the new forecast reveals.
Ойдан шығарылған жоба- Building
- Three stories: retail on a concrete podium, two wood-frame apartment floors
- Contract
- AIA A101 stipulated sum (one fixed price) with A201 general conditions; revenue counted under ASC 606
- Period
- October 2026 month-end close
- ERP-дегі жұмыс
- Тапсырмалар: 4, шамамен 2 сағ 10 мин
Кім кімге не береді
Every arrow is a figure or a document that reaches your desk or leaves it, and the task where that happens.
Сізге келеді
- Project managerYour firm
- Cost to complete1-тапсырма
- Reforecast4-тапсырма
- The ownerOwner
- Change orders, signed and unsigned2-тапсырма
- SuperintendentYour firm
- Stairs delivered, not installed3-тапсырма
Сізден кетеді
- CVR month 2026-101-тапсырма
- Earned revenue and gross profit2-тапсырма
- Over/under billing3-тапсырма
- Loss provision4-тапсырма
Жоба бойынша жолыңыз
Two tasks build the WIP line, one checks it against stored material and billing, one tests it against a loss. Start with task 1: from the job cost report you work out cost to date, the forecast final cost and the percent complete.
The WIP line
1-тапсырма · 30 мин
Бүгінге дейінгі шығын, аяқталу кезіндегі болжам, орындалу пайызы
- Нәтиже
- Cost to date, estimate at completion, percent complete
- Құжат
- Job cost report, October 2026
- ERP-де
- Cost-Value Reconciliation
The WIP line
2-тапсырма · 30 мин
Тапқан түсім және жалпы пайда
- Нәтиже
- Contract value, earned revenue and both gross profits
- Құжат
- Contract sum and change orders CO-01 to CO-03
- ERP-де
- Cost-Value Reconciliation, REV head
Billing check
3-тапсырма · 35 мин
Орнатылмаған материал және артық/кем биллинг
- Нәтиже
- Revenue with the stairs at cost, and the billing position
- Құжат
- AIA G702, pay application 9 (the monthly bill)
- ERP-де
- Cost-Value Reconciliation, Edit cost head
Reforecast
4-тапсырма · 35 мин
Залалды жұмыс: бүкіл залал қазір
- Нәтиже
- The provision for anticipated loss (the whole expected loss, booked now)
- Құжат
- Reforecast before the close
- ERP-де
- Cost-Value Reconciliation, LOSS head
How cost turns into revenue on a WIP line
Each bar is one task, in the order the October close runs.
Көкпен — тапсырма қосатын бөлік; сұрмен — алдыңғы қадамнан келгені.
Қысқаша. Cost against cost for the percent. Stored material at cost, no margin. Gross billings against earned revenue. A loss goes in whole, the month you see it.