Introduktion till kursen · 3 min
PIA-rapport: färdigställandegrad och över-/underfakturering (USA)
You are the project accountant at a general contractor building a block of shops with apartments above. Each month the firm reports every open job on one line of its work-in-progress (WIP) schedule, which banks and bonding companies read. In four tasks you close October for this job: how complete it is, how much revenue it has earned, whether billing runs ahead of the work, and the loss the new forecast reveals.
Fiktivt projekt- Building
- Three stories: retail on a concrete podium, two wood-frame apartment floors
- Contract
- AIA A101 stipulated sum (one fixed price) with A201 general conditions; revenue counted under ASC 606
- Period
- October 2026 month-end close
- Arbete i ERP
- 4 uppgifter, cirka 2 h 10 min
Vem lämnar vad till vem
Every arrow is a figure or a document that reaches your desk or leaves it, and the task where that happens.
Kommer till dig
- Project managerYour firm
- Cost to completeUppgift 1
- ReforecastUppgift 4
- The ownerOwner
- Change orders, signed and unsignedUppgift 2
- SuperintendentYour firm
- Stairs delivered, not installedUppgift 3
Går från dig
- CVR month 2026-10Uppgift 1
- Earned revenue and gross profitUppgift 2
- Over/under billingUppgift 3
- Loss provisionUppgift 4
Din väg genom projektet
Two tasks build the WIP line, one checks it against stored material and billing, one tests it against a loss. Start with task 1: from the job cost report you work out cost to date, the forecast final cost and the percent complete.
The WIP line
Uppgift 1 · 30 min
Kostnad hittills, prognostiserad slutkostnad, färdigställandegrad
- Du tar fram
- Cost to date, estimate at completion, percent complete
- Dokument
- Job cost report, October 2026
- I ERP
- Cost-Value Reconciliation
The WIP line
Uppgift 2 · 30 min
Upparbetad intäkt och bruttovinst
- Du tar fram
- Contract value, earned revenue and both gross profits
- Dokument
- Contract sum and change orders CO-01 to CO-03
- I ERP
- Cost-Value Reconciliation, REV head
Billing check
Uppgift 3 · 35 min
Oinstallerat material och över-/underfakturering
- Du tar fram
- Revenue with the stairs at cost, and the billing position
- Dokument
- AIA G702, pay application 9 (the monthly bill)
- I ERP
- Cost-Value Reconciliation, Edit cost head
Reforecast
Uppgift 4 · 35 min
Ett förlustprojekt: hela förlusten nu
- Du tar fram
- The provision for anticipated loss (the whole expected loss, booked now)
- Dokument
- Reforecast before the close
- I ERP
- Cost-Value Reconciliation, LOSS head
How cost turns into revenue on a WIP line
Each bar is one task, in the order the October close runs.
Blått är det uppgiften lägger till; grått följer med från tidigare.
Kort sagt. Cost against cost for the percent. Stored material at cost, no margin. Gross billings against earned revenue. A loss goes in whole, the month you see it.