OHW-schema: voltooiingspercentage en over-/onderfacturatie (VS)
You are the project accountant at a general contractor building a block of shops with apartments above. Each month the firm reports every open job on one line of its work-in-progress (WIP) schedule, which banks and bonding companies read. In four tasks you close October for this job: how complete it is, how much revenue it has earned, whether billing runs ahead of the work, and the loss the new forecast reveals.
Fictief project- Building
- Three stories: retail on a concrete podium, two wood-frame apartment floors
- Contract
- AIA A101 stipulated sum (one fixed price) with A201 general conditions; revenue counted under ASC 606
- Period
- October 2026 month-end close
- Werk in de ERP
- 4 opdrachten, ongeveer 2 u 10 min
Wie geeft wat aan wie
Every arrow is a figure or a document that reaches your desk or leaves it, and the task where that happens.
Komt bij u
- Project managerYour firm
- Cost to completeOpdracht 1
- ReforecastOpdracht 4
- The ownerOwner
- Change orders, signed and unsignedOpdracht 2
- SuperintendentYour firm
- Stairs delivered, not installedOpdracht 3
Gaat van u uit
- CVR month 2026-10Opdracht 1
- Earned revenue and gross profitOpdracht 2
- Over/under billingOpdracht 3
- Loss provisionOpdracht 4
Uw route door het project
Two tasks build the WIP line, one checks it against stored material and billing, one tests it against a loss. Start with task 1: from the job cost report you work out cost to date, the forecast final cost and the percent complete.
The WIP line
Opdracht 1 · 30 min
Kosten tot op heden, verwachte eindkosten, voltooiingspercentage
- U levert
- Cost to date, estimate at completion, percent complete
- Document
- Job cost report, October 2026
- In de ERP
- Cost-Value Reconciliation
The WIP line
Opdracht 2 · 30 min
Verdiende omzet en brutowinst
- U levert
- Contract value, earned revenue and both gross profits
- Document
- Contract sum and change orders CO-01 to CO-03
- In de ERP
- Cost-Value Reconciliation, REV head
Billing check
Opdracht 3 · 35 min
Niet-geïnstalleerd materiaal en over-/onderfacturering
- U levert
- Revenue with the stairs at cost, and the billing position
- Document
- AIA G702, pay application 9 (the monthly bill)
- In de ERP
- Cost-Value Reconciliation, Edit cost head
Reforecast
Opdracht 4 · 35 min
Een verliesproject: het volledige verlies nu
- U levert
- The provision for anticipated loss (the whole expected loss, booked now)
- Document
- Reforecast before the close
- In de ERP
- Cost-Value Reconciliation, LOSS head
How cost turns into revenue on a WIP line
Each bar is one task, in the order the October close runs.
Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.
Kort gezegd. Cost against cost for the percent. Stored material at cost, no margin. Gross billings against earned revenue. A loss goes in whole, the month you see it.