OpenConstruction Academy
Inloggen / Registreren
NL

Inleiding tot de cursus · 3 min

OHW-schema: voltooiingspercentage en over-/onderfacturatie (VS)

You are the project accountant at a general contractor building a block of shops with apartments above. Each month the firm reports every open job on one line of its work-in-progress (WIP) schedule, which banks and bonding companies read. In four tasks you close October for this job: how complete it is, how much revenue it has earned, whether billing runs ahead of the work, and the loss the new forecast reveals.

Start opdracht 1

A three-story building on a fenced site: a concrete podium with sheathed wood-frame floors above, a steel stair resting on pallets by the fence and three workers in hi-vis vests on the street.Fictief project
Quillfield CommonsRetail podium and two floors of apartments
Building
Three stories: retail on a concrete podium, two wood-frame apartment floors
Contract
AIA A101 stipulated sum (one fixed price) with A201 general conditions; revenue counted under ASC 606
Period
October 2026 month-end close
Werk in de ERP
4 opdrachten, ongeveer 2 u 10 min

Wie geeft wat aan wie

Every arrow is a figure or a document that reaches your desk or leaves it, and the task where that happens.

Komt bij u

  • Project managerYour firm
    • Cost to completeOpdracht 1
    • ReforecastOpdracht 4
  • The ownerOwner
    • Change orders, signed and unsignedOpdracht 2
  • SuperintendentYour firm
    • Stairs delivered, not installedOpdracht 3
UProject accountant, general contractor

Gaat van u uit

    • CVR month 2026-10Opdracht 1
    ControllerYour firm
    • Earned revenue and gross profitOpdracht 2
    • Over/under billingOpdracht 3
    Bank and suretyRead the WIP schedule
    • Loss provisionOpdracht 4
    Outside auditorCPA firm

Uw route door het project

Two tasks build the WIP line, one checks it against stored material and billing, one tests it against a loss. Start with task 1: from the job cost report you work out cost to date, the forecast final cost and the percent complete.

  1. The WIP line

    Opdracht 1 · 30 min

    Kosten tot op heden, verwachte eindkosten, voltooiingspercentage

    U levert
    Cost to date, estimate at completion, percent complete
    Document
    Job cost report, October 2026
    In de ERP
    Cost-Value Reconciliation
  2. The WIP line

    Opdracht 2 · 30 min

    Verdiende omzet en brutowinst

    U levert
    Contract value, earned revenue and both gross profits
    Document
    Contract sum and change orders CO-01 to CO-03
    In de ERP
    Cost-Value Reconciliation, REV head
  3. Billing check

    Opdracht 3 · 35 min

    Niet-geïnstalleerd materiaal en over-/onderfacturering

    U levert
    Revenue with the stairs at cost, and the billing position
    Document
    AIA G702, pay application 9 (the monthly bill)
    In de ERP
    Cost-Value Reconciliation, Edit cost head
  4. Reforecast

    Opdracht 4 · 35 min

    Een verliesproject: het volledige verlies nu

    U levert
    The provision for anticipated loss (the whole expected loss, booked now)
    Document
    Reforecast before the close
    In de ERP
    Cost-Value Reconciliation, LOSS head

How cost turns into revenue on a WIP line

Each bar is one task, in the order the October close runs.

Cost to completeCost to date
Opdracht 1Percent completeCost to date over the estimate at completion. Cost against cost, nothing else.
Still to earnGross profitCost to date
Opdracht 2Earned revenueContract value times that ratio. Approved change orders in, unsigned ones out.
Over billingEarned revenue
Opdracht 3Billing positionEarned revenue, with stored material at cost, against what was billed on the G702 before retainage.
Loss, booked nowContract value
Opdracht 4Loss provisionWhen the estimate passes the contract value, the whole loss goes in this month.

Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.

Kort gezegd. Cost against cost for the percent. Stored material at cost, no margin. Gross billings against earned revenue. A loss goes in whole, the month you see it.