کورس کا تعارف · 3 منٹ
WIP شیڈول: تکمیل کا فیصد اور زیادہ/کم بلنگ (امریکہ)
You are the project accountant at a general contractor building a block of shops with apartments above. Each month the firm reports every open job on one line of its work-in-progress (WIP) schedule, which banks and bonding companies read. In four tasks you close October for this job: how complete it is, how much revenue it has earned, whether billing runs ahead of the work, and the loss the new forecast reveals.
فرضی پراجیکٹ- Building
- Three stories: retail on a concrete podium, two wood-frame apartment floors
- Contract
- AIA A101 stipulated sum (one fixed price) with A201 general conditions; revenue counted under ASC 606
- Period
- October 2026 month-end close
- ERP میں کام
- 4 ٹاسک، تقریباً 2 گھنٹے 10 منٹ
کون کس کو کیا دیتا ہے
Every arrow is a figure or a document that reaches your desk or leaves it, and the task where that happens.
آپ کے پاس آتا ہے
- Project managerYour firm
- Cost to completeٹاسک 1
- Reforecastٹاسک 4
- The ownerOwner
- Change orders, signed and unsignedٹاسک 2
- SuperintendentYour firm
- Stairs delivered, not installedٹاسک 3
آپ سے جاتا ہے
- CVR month 2026-10ٹاسک 1
- Earned revenue and gross profitٹاسک 2
- Over/under billingٹاسک 3
- Loss provisionٹاسک 4
پراجیکٹ میں آپ کا راستہ
Two tasks build the WIP line, one checks it against stored material and billing, one tests it against a loss. Start with task 1: from the job cost report you work out cost to date, the forecast final cost and the percent complete.
The WIP line
ٹاسک 1 · 30 منٹ
اب تک کی لاگت، تکمیل پر تخمینہ، تکمیل کا فیصد
- آپ کا نتیجہ
- Cost to date, estimate at completion, percent complete
- دستاویز
- Job cost report, October 2026
- ERP میں
- Cost-Value Reconciliation
The WIP line
ٹاسک 2 · 30 منٹ
کمائی گئی آمدنی اور مجموعی منافع
- آپ کا نتیجہ
- Contract value, earned revenue and both gross profits
- دستاویز
- Contract sum and change orders CO-01 to CO-03
- ERP میں
- Cost-Value Reconciliation, REV head
Billing check
ٹاسک 3 · 35 منٹ
غیر نصب شدہ میٹیریل اور اوور/انڈر بلنگ
- آپ کا نتیجہ
- Revenue with the stairs at cost, and the billing position
- دستاویز
- AIA G702, pay application 9 (the monthly bill)
- ERP میں
- Cost-Value Reconciliation, Edit cost head
Reforecast
ٹاسک 4 · 35 منٹ
خسارے والی جاب: پورا خسارہ ابھی
- آپ کا نتیجہ
- The provision for anticipated loss (the whole expected loss, booked now)
- دستاویز
- Reforecast before the close
- ERP میں
- Cost-Value Reconciliation, LOSS head
How cost turns into revenue on a WIP line
Each bar is one task, in the order the October close runs.
نیلا وہ ہے جو ٹاسک شامل کرتا ہے؛ سرمئی پچھلے مرحلے سے آیا ہے۔
مختصراً. Cost against cost for the percent. Stored material at cost, no margin. Gross billings against earned revenue. A loss goes in whole, the month you see it.