کورس کا تعارف · 3 منٹ

WIP شیڈول: تکمیل کا فیصد اور زیادہ/کم بلنگ (امریکہ)

You are the project accountant at a general contractor building a block of shops with apartments above. Each month the firm reports every open job on one line of its work-in-progress (WIP) schedule, which banks and bonding companies read. In four tasks you close October for this job: how complete it is, how much revenue it has earned, whether billing runs ahead of the work, and the loss the new forecast reveals.

ٹاسک 1 شروع کریں

A three-story building on a fenced site: a concrete podium with sheathed wood-frame floors above, a steel stair resting on pallets by the fence and three workers in hi-vis vests on the street.فرضی پراجیکٹ
Quillfield CommonsRetail podium and two floors of apartments
Building
Three stories: retail on a concrete podium, two wood-frame apartment floors
Contract
AIA A101 stipulated sum (one fixed price) with A201 general conditions; revenue counted under ASC 606
Period
October 2026 month-end close
ERP میں کام
4 ٹاسک، تقریباً 2 گھنٹے 10 منٹ

کون کس کو کیا دیتا ہے

Every arrow is a figure or a document that reaches your desk or leaves it, and the task where that happens.

آپ کے پاس آتا ہے

  • Project managerYour firm
    • Cost to completeٹاسک 1
    • Reforecastٹاسک 4
  • The ownerOwner
    • Change orders, signed and unsignedٹاسک 2
  • SuperintendentYour firm
    • Stairs delivered, not installedٹاسک 3
آپProject accountant, general contractor

آپ سے جاتا ہے

    • CVR month 2026-10ٹاسک 1
    ControllerYour firm
    • Earned revenue and gross profitٹاسک 2
    • Over/under billingٹاسک 3
    Bank and suretyRead the WIP schedule
    • Loss provisionٹاسک 4
    Outside auditorCPA firm

پراجیکٹ میں آپ کا راستہ

Two tasks build the WIP line, one checks it against stored material and billing, one tests it against a loss. Start with task 1: from the job cost report you work out cost to date, the forecast final cost and the percent complete.

  1. The WIP line

    ٹاسک 1 · 30 منٹ

    اب تک کی لاگت، تکمیل پر تخمینہ، تکمیل کا فیصد

    آپ کا نتیجہ
    Cost to date, estimate at completion, percent complete
    دستاویز
    Job cost report, October 2026
    ERP میں
    Cost-Value Reconciliation
  2. The WIP line

    ٹاسک 2 · 30 منٹ

    کمائی گئی آمدنی اور مجموعی منافع

    آپ کا نتیجہ
    Contract value, earned revenue and both gross profits
    دستاویز
    Contract sum and change orders CO-01 to CO-03
    ERP میں
    Cost-Value Reconciliation, REV head
  3. Billing check

    ٹاسک 3 · 35 منٹ

    غیر نصب شدہ میٹیریل اور اوور/انڈر بلنگ

    آپ کا نتیجہ
    Revenue with the stairs at cost, and the billing position
    دستاویز
    AIA G702, pay application 9 (the monthly bill)
    ERP میں
    Cost-Value Reconciliation, Edit cost head
  4. Reforecast

    ٹاسک 4 · 35 منٹ

    خسارے والی جاب: پورا خسارہ ابھی

    آپ کا نتیجہ
    The provision for anticipated loss (the whole expected loss, booked now)
    دستاویز
    Reforecast before the close
    ERP میں
    Cost-Value Reconciliation, LOSS head

How cost turns into revenue on a WIP line

Each bar is one task, in the order the October close runs.

Cost to completeCost to date
ٹاسک 1Percent completeCost to date over the estimate at completion. Cost against cost, nothing else.
Still to earnGross profitCost to date
ٹاسک 2Earned revenueContract value times that ratio. Approved change orders in, unsigned ones out.
Over billingEarned revenue
ٹاسک 3Billing positionEarned revenue, with stored material at cost, against what was billed on the G702 before retainage.
Loss, booked nowContract value
ٹاسک 4Loss provisionWhen the estimate passes the contract value, the whole loss goes in this month.

نیلا وہ ہے جو ٹاسک شامل کرتا ہے؛ سرمئی پچھلے مرحلے سے آیا ہے۔

مختصراً. Cost against cost for the percent. Stored material at cost, no margin. Gross billings against earned revenue. A loss goes in whole, the month you see it.