מבוא לקורס · 3 דק׳
לוח WIP: אחוז השלמה וחיוב יתר/חסר (ארה״ב)
You are the project accountant at a general contractor building a block of shops with apartments above. Each month the firm reports every open job on one line of its work-in-progress (WIP) schedule, which banks and bonding companies read. In four tasks you close October for this job: how complete it is, how much revenue it has earned, whether billing runs ahead of the work, and the loss the new forecast reveals.
פרויקט בדיוני- Building
- Three stories: retail on a concrete podium, two wood-frame apartment floors
- Contract
- AIA A101 stipulated sum (one fixed price) with A201 general conditions; revenue counted under ASC 606
- Period
- October 2026 month-end close
- עבודה ב-ERP
- 4 משימות, כ-2 ש׳ 10 דק׳
מי מעביר מה למי
Every arrow is a figure or a document that reaches your desk or leaves it, and the task where that happens.
מגיע אליכם
- Project managerYour firm
- Cost to completeמשימה 1
- Reforecastמשימה 4
- The ownerOwner
- Change orders, signed and unsignedמשימה 2
- SuperintendentYour firm
- Stairs delivered, not installedמשימה 3
יוצא מכם
- CVR month 2026-10משימה 1
- Earned revenue and gross profitמשימה 2
- Over/under billingמשימה 3
- Loss provisionמשימה 4
המסלול שלכם בפרויקט
Two tasks build the WIP line, one checks it against stored material and billing, one tests it against a loss. Start with task 1: from the job cost report you work out cost to date, the forecast final cost and the percent complete.
The WIP line
משימה 1 · 30 דק׳
עלות עד כה, אומדן בהשלמה, אחוז השלמה
- התוצר שלכם
- Cost to date, estimate at completion, percent complete
- מסמך
- Job cost report, October 2026
- ב-ERP
- Cost-Value Reconciliation
The WIP line
משימה 2 · 30 דק׳
הכנסה שהורווחה ורווח גולמי
- התוצר שלכם
- Contract value, earned revenue and both gross profits
- מסמך
- Contract sum and change orders CO-01 to CO-03
- ב-ERP
- Cost-Value Reconciliation, REV head
Billing check
משימה 3 · 35 דק׳
חומר שטרם הותקן וחיוב יתר/חסר
- התוצר שלכם
- Revenue with the stairs at cost, and the billing position
- מסמך
- AIA G702, pay application 9 (the monthly bill)
- ב-ERP
- Cost-Value Reconciliation, Edit cost head
Reforecast
משימה 4 · 35 דק׳
עבודה מפסידה: כל ההפסד עכשיו
- התוצר שלכם
- The provision for anticipated loss (the whole expected loss, booked now)
- מסמך
- Reforecast before the close
- ב-ERP
- Cost-Value Reconciliation, LOSS head
How cost turns into revenue on a WIP line
Each bar is one task, in the order the October close runs.
בכחול מה שהמשימה מוסיפה; באפור מה שעבר מהשלב הקודם.
בקצרה. Cost against cost for the percent. Stored material at cost, no margin. Gross billings against earned revenue. A loss goes in whole, the month you see it.