WIP тизмеси: бүтүү пайызы жана ашык/кем эсеп чыгаруу (АКШ)
You are the project accountant at a general contractor building a block of shops with apartments above. Each month the firm reports every open job on one line of its work-in-progress (WIP) schedule, which banks and bonding companies read. In four tasks you close October for this job: how complete it is, how much revenue it has earned, whether billing runs ahead of the work, and the loss the new forecast reveals.
Ойдон чыгарылган долбоор- Building
- Three stories: retail on a concrete podium, two wood-frame apartment floors
- Contract
- AIA A101 stipulated sum (one fixed price) with A201 general conditions; revenue counted under ASC 606
- Period
- October 2026 month-end close
- ERPдеги иш
- Тапшырмалар: 4, болжол менен 2 саат 10 мүн
Ким кимге эмне берет
Every arrow is a figure or a document that reaches your desk or leaves it, and the task where that happens.
Сизге келет
- Project managerYour firm
- Cost to complete1-тапшырма
- Reforecast4-тапшырма
- The ownerOwner
- Change orders, signed and unsigned2-тапшырма
- SuperintendentYour firm
- Stairs delivered, not installed3-тапшырма
Сизден кетет
- CVR month 2026-101-тапшырма
- Earned revenue and gross profit2-тапшырма
- Over/under billing3-тапшырма
- Loss provision4-тапшырма
Долбоор боюнча жолуңуз
Two tasks build the WIP line, one checks it against stored material and billing, one tests it against a loss. Start with task 1: from the job cost report you work out cost to date, the forecast final cost and the percent complete.
The WIP line
1-тапшырма · 30 мүн
Ушул күнгө чейинки чыгым, аяктоодогу болжолдуу чыгым, даярдык пайызы
- Натыйжа
- Cost to date, estimate at completion, percent complete
- Документ
- Job cost report, October 2026
- ERPде
- Cost-Value Reconciliation
The WIP line
2-тапшырма · 30 мүн
Тапкан киреше жана дүң пайда
- Натыйжа
- Contract value, earned revenue and both gross profits
- Документ
- Contract sum and change orders CO-01 to CO-03
- ERPде
- Cost-Value Reconciliation, REV head
Billing check
3-тапшырма · 35 мүн
Орнотулбаган материал жана ашыкча/жетишсиз эсеп-фактура
- Натыйжа
- Revenue with the stairs at cost, and the billing position
- Документ
- AIA G702, pay application 9 (the monthly bill)
- ERPде
- Cost-Value Reconciliation, Edit cost head
Reforecast
4-тапшырма · 35 мүн
Зыяндуу долбоор: бүт зыян азыр
- Натыйжа
- The provision for anticipated loss (the whole expected loss, booked now)
- Документ
- Reforecast before the close
- ERPде
- Cost-Value Reconciliation, LOSS head
How cost turns into revenue on a WIP line
Each bar is one task, in the order the October close runs.
Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.
Кыскача. Cost against cost for the percent. Stored material at cost, no margin. Gross billings against earned revenue. A loss goes in whole, the month you see it.