Přehled nedokončené výroby: procento dokončení a pře/nedofakturace (USA)

You are the project accountant at a general contractor building a block of shops with apartments above. Each month the firm reports every open job on one line of its work-in-progress (WIP) schedule, which banks and bonding companies read. In four tasks you close October for this job: how complete it is, how much revenue it has earned, whether billing runs ahead of the work, and the loss the new forecast reveals.

Začít úlohu 1

A three-story building on a fenced site: a concrete podium with sheathed wood-frame floors above, a steel stair resting on pallets by the fence and three workers in hi-vis vests on the street.Smyšlený projekt
Quillfield CommonsRetail podium and two floors of apartments
Building
Three stories: retail on a concrete podium, two wood-frame apartment floors
Contract
AIA A101 stipulated sum (one fixed price) with A201 general conditions; revenue counted under ASC 606
Period
October 2026 month-end close
Práce v ERP
Úlohy: 4, asi 2 h 10 min

Kdo komu co předává

Every arrow is a figure or a document that reaches your desk or leaves it, and the task where that happens.

Přichází k vám

  • Project managerYour firm
    • Cost to completeÚloha 1
    • ReforecastÚloha 4
  • The ownerOwner
    • Change orders, signed and unsignedÚloha 2
  • SuperintendentYour firm
    • Stairs delivered, not installedÚloha 3
VyProject accountant, general contractor

Odchází od vás

    • CVR month 2026-10Úloha 1
    ControllerYour firm
    • Earned revenue and gross profitÚloha 2
    • Over/under billingÚloha 3
    Bank and suretyRead the WIP schedule
    • Loss provisionÚloha 4
    Outside auditorCPA firm

Vaše cesta zakázkou

Two tasks build the WIP line, one checks it against stored material and billing, one tests it against a loss. Start with task 1: from the job cost report you work out cost to date, the forecast final cost and the percent complete.

  1. The WIP line

    Úloha 1 · 30 min

    Dosavadní náklady, odhad po dokončení, procento dokončení

    Výstup
    Cost to date, estimate at completion, percent complete
    Dokument
    Job cost report, October 2026
    V ERP
    Cost-Value Reconciliation
  2. The WIP line

    Úloha 2 · 30 min

    Realizované výnosy a hrubý zisk

    Výstup
    Contract value, earned revenue and both gross profits
    Dokument
    Contract sum and change orders CO-01 to CO-03
    V ERP
    Cost-Value Reconciliation, REV head
  3. Billing check

    Úloha 3 · 35 min

    Nenainstalovaný materiál a nadměrná/nedostatečná fakturace

    Výstup
    Revenue with the stairs at cost, and the billing position
    Dokument
    AIA G702, pay application 9 (the monthly bill)
    V ERP
    Cost-Value Reconciliation, Edit cost head
  4. Reforecast

    Úloha 4 · 35 min

    Ztrátová zakázka: celá ztráta ihned

    Výstup
    The provision for anticipated loss (the whole expected loss, booked now)
    Dokument
    Reforecast before the close
    V ERP
    Cost-Value Reconciliation, LOSS head

How cost turns into revenue on a WIP line

Each bar is one task, in the order the October close runs.

Cost to completeCost to date
Úloha 1Percent completeCost to date over the estimate at completion. Cost against cost, nothing else.
Still to earnGross profitCost to date
Úloha 2Earned revenueContract value times that ratio. Approved change orders in, unsigned ones out.
Over billingEarned revenue
Úloha 3Billing positionEarned revenue, with stored material at cost, against what was billed on the G702 before retainage.
Loss, booked nowContract value
Úloha 4Loss provisionWhen the estimate passes the contract value, the whole loss goes in this month.

Modře je to, co úloha přidává; šedě to, co se přenáší z dřívějška.

Stručně. Cost against cost for the percent. Stored material at cost, no margin. Gross billings against earned revenue. A loss goes in whole, the month you see it.