Úvod do kurzu · 3 min
Přehled nedokončené výroby: procento dokončení a pře/nedofakturace (USA)
You are the project accountant at a general contractor building a block of shops with apartments above. Each month the firm reports every open job on one line of its work-in-progress (WIP) schedule, which banks and bonding companies read. In four tasks you close October for this job: how complete it is, how much revenue it has earned, whether billing runs ahead of the work, and the loss the new forecast reveals.
Smyšlený projekt- Building
- Three stories: retail on a concrete podium, two wood-frame apartment floors
- Contract
- AIA A101 stipulated sum (one fixed price) with A201 general conditions; revenue counted under ASC 606
- Period
- October 2026 month-end close
- Práce v ERP
- Úlohy: 4, asi 2 h 10 min
Kdo komu co předává
Every arrow is a figure or a document that reaches your desk or leaves it, and the task where that happens.
Přichází k vám
- Project managerYour firm
- Cost to completeÚloha 1
- ReforecastÚloha 4
- The ownerOwner
- Change orders, signed and unsignedÚloha 2
- SuperintendentYour firm
- Stairs delivered, not installedÚloha 3
Odchází od vás
- CVR month 2026-10Úloha 1
- Earned revenue and gross profitÚloha 2
- Over/under billingÚloha 3
- Loss provisionÚloha 4
Vaše cesta zakázkou
Two tasks build the WIP line, one checks it against stored material and billing, one tests it against a loss. Start with task 1: from the job cost report you work out cost to date, the forecast final cost and the percent complete.
The WIP line
Úloha 1 · 30 min
Dosavadní náklady, odhad po dokončení, procento dokončení
- Výstup
- Cost to date, estimate at completion, percent complete
- Dokument
- Job cost report, October 2026
- V ERP
- Cost-Value Reconciliation
The WIP line
Úloha 2 · 30 min
Realizované výnosy a hrubý zisk
- Výstup
- Contract value, earned revenue and both gross profits
- Dokument
- Contract sum and change orders CO-01 to CO-03
- V ERP
- Cost-Value Reconciliation, REV head
Billing check
Úloha 3 · 35 min
Nenainstalovaný materiál a nadměrná/nedostatečná fakturace
- Výstup
- Revenue with the stairs at cost, and the billing position
- Dokument
- AIA G702, pay application 9 (the monthly bill)
- V ERP
- Cost-Value Reconciliation, Edit cost head
Reforecast
Úloha 4 · 35 min
Ztrátová zakázka: celá ztráta ihned
- Výstup
- The provision for anticipated loss (the whole expected loss, booked now)
- Dokument
- Reforecast before the close
- V ERP
- Cost-Value Reconciliation, LOSS head
How cost turns into revenue on a WIP line
Each bar is one task, in the order the October close runs.
Modře je to, co úloha přidává; šedě to, co se přenáší z dřívějška.
Stručně. Cost against cost for the percent. Stored material at cost, no margin. Gross billings against earned revenue. A loss goes in whole, the month you see it.