Kurssin johdanto · 3 min
WIP-aikataulu: valmiusaste ja yli-/alilaskutus (USA)
You are the project accountant at a general contractor building a block of shops with apartments above. Each month the firm reports every open job on one line of its work-in-progress (WIP) schedule, which banks and bonding companies read. In four tasks you close October for this job: how complete it is, how much revenue it has earned, whether billing runs ahead of the work, and the loss the new forecast reveals.
Kuvitteellinen hanke- Building
- Three stories: retail on a concrete podium, two wood-frame apartment floors
- Contract
- AIA A101 stipulated sum (one fixed price) with A201 general conditions; revenue counted under ASC 606
- Period
- October 2026 month-end close
- Työ ERP:ssä
- Tehtäviä 4, noin 2 t 10 min
Kuka antaa mitä kenelle
Every arrow is a figure or a document that reaches your desk or leaves it, and the task where that happens.
Tulee sinulle
- Project managerYour firm
- Cost to completeTehtävä 1
- ReforecastTehtävä 4
- The ownerOwner
- Change orders, signed and unsignedTehtävä 2
- SuperintendentYour firm
- Stairs delivered, not installedTehtävä 3
Lähtee sinulta
- CVR month 2026-10Tehtävä 1
- Earned revenue and gross profitTehtävä 2
- Over/under billingTehtävä 3
- Loss provisionTehtävä 4
Reittisi hankkeen läpi
Two tasks build the WIP line, one checks it against stored material and billing, one tests it against a loss. Start with task 1: from the job cost report you work out cost to date, the forecast final cost and the percent complete.
The WIP line
Tehtävä 1 · 30 min
Kertyneet kustannukset, valmistumisarvio, valmiusaste
- Tuotat
- Cost to date, estimate at completion, percent complete
- Asiakirja
- Job cost report, October 2026
- ERP:ssä
- Cost-Value Reconciliation
The WIP line
Tehtävä 2 · 30 min
Tuloutettu liikevaihto ja bruttokate
- Tuotat
- Contract value, earned revenue and both gross profits
- Asiakirja
- Contract sum and change orders CO-01 to CO-03
- ERP:ssä
- Cost-Value Reconciliation, REV head
Billing check
Tehtävä 3 · 35 min
Asentamaton materiaali ja yli-/alilaskutus
- Tuotat
- Revenue with the stairs at cost, and the billing position
- Asiakirja
- AIA G702, pay application 9 (the monthly bill)
- ERP:ssä
- Cost-Value Reconciliation, Edit cost head
Reforecast
Tehtävä 4 · 35 min
Tappioprojekti: koko tappio nyt
- Tuotat
- The provision for anticipated loss (the whole expected loss, booked now)
- Asiakirja
- Reforecast before the close
- ERP:ssä
- Cost-Value Reconciliation, LOSS head
How cost turns into revenue on a WIP line
Each bar is one task, in the order the October close runs.
Sininen on se, mitä tehtävä lisää; harmaa tulee aiemmasta.
Lyhyesti. Cost against cost for the percent. Stored material at cost, no margin. Gross billings against earned revenue. A loss goes in whole, the month you see it.