Introduktion til kurset · 3 min

WIP-oversigt: færdiggørelsesgrad og over-/underfakturering (USA)

You are the project accountant at a general contractor building a block of shops with apartments above. Each month the firm reports every open job on one line of its work-in-progress (WIP) schedule, which banks and bonding companies read. In four tasks you close October for this job: how complete it is, how much revenue it has earned, whether billing runs ahead of the work, and the loss the new forecast reveals.

Start opgave 1

A three-story building on a fenced site: a concrete podium with sheathed wood-frame floors above, a steel stair resting on pallets by the fence and three workers in hi-vis vests on the street.Fiktivt projekt
Quillfield CommonsRetail podium and two floors of apartments
Building
Three stories: retail on a concrete podium, two wood-frame apartment floors
Contract
AIA A101 stipulated sum (one fixed price) with A201 general conditions; revenue counted under ASC 606
Period
October 2026 month-end close
Arbejde i ERP
4 opgaver, cirka 2 t 10 min

Hvem giver hvad til hvem

Every arrow is a figure or a document that reaches your desk or leaves it, and the task where that happens.

Kommer til dig

  • Project managerYour firm
    • Cost to completeOpgave 1
    • ReforecastOpgave 4
  • The ownerOwner
    • Change orders, signed and unsignedOpgave 2
  • SuperintendentYour firm
    • Stairs delivered, not installedOpgave 3
DigProject accountant, general contractor

Går fra dig

    • CVR month 2026-10Opgave 1
    ControllerYour firm
    • Earned revenue and gross profitOpgave 2
    • Over/under billingOpgave 3
    Bank and suretyRead the WIP schedule
    • Loss provisionOpgave 4
    Outside auditorCPA firm

Din vej gennem sagen

Two tasks build the WIP line, one checks it against stored material and billing, one tests it against a loss. Start with task 1: from the job cost report you work out cost to date, the forecast final cost and the percent complete.

  1. The WIP line

    Opgave 1 · 30 min

    Omkostninger til dato, estimat ved færdiggørelse, færdiggørelsesgrad

    Du leverer
    Cost to date, estimate at completion, percent complete
    Dokument
    Job cost report, October 2026
    I ERP
    Cost-Value Reconciliation
  2. The WIP line

    Opgave 2 · 30 min

    Optjent omsætning og bruttofortjeneste

    Du leverer
    Contract value, earned revenue and both gross profits
    Dokument
    Contract sum and change orders CO-01 to CO-03
    I ERP
    Cost-Value Reconciliation, REV head
  3. Billing check

    Opgave 3 · 35 min

    Ikke-installerede materialer og over-/underfakturering

    Du leverer
    Revenue with the stairs at cost, and the billing position
    Dokument
    AIA G702, pay application 9 (the monthly bill)
    I ERP
    Cost-Value Reconciliation, Edit cost head
  4. Reforecast

    Opgave 4 · 35 min

    Et tabsprojekt: hele tabet nu

    Du leverer
    The provision for anticipated loss (the whole expected loss, booked now)
    Dokument
    Reforecast before the close
    I ERP
    Cost-Value Reconciliation, LOSS head

How cost turns into revenue on a WIP line

Each bar is one task, in the order the October close runs.

Cost to completeCost to date
Opgave 1Percent completeCost to date over the estimate at completion. Cost against cost, nothing else.
Still to earnGross profitCost to date
Opgave 2Earned revenueContract value times that ratio. Approved change orders in, unsigned ones out.
Over billingEarned revenue
Opgave 3Billing positionEarned revenue, with stored material at cost, against what was billed on the G702 before retainage.
Loss, booked nowContract value
Opgave 4Loss provisionWhen the estimate passes the contract value, the whole loss goes in this month.

Blå er det, opgaven tilføjer; grå er overført fra før.

Kort sagt. Cost against cost for the percent. Stored material at cost, no margin. Gross billings against earned revenue. A loss goes in whole, the month you see it.