Introduktion til kurset · 3 min
WIP-oversigt: færdiggørelsesgrad og over-/underfakturering (USA)
You are the project accountant at a general contractor building a block of shops with apartments above. Each month the firm reports every open job on one line of its work-in-progress (WIP) schedule, which banks and bonding companies read. In four tasks you close October for this job: how complete it is, how much revenue it has earned, whether billing runs ahead of the work, and the loss the new forecast reveals.
Fiktivt projekt- Building
- Three stories: retail on a concrete podium, two wood-frame apartment floors
- Contract
- AIA A101 stipulated sum (one fixed price) with A201 general conditions; revenue counted under ASC 606
- Period
- October 2026 month-end close
- Arbejde i ERP
- 4 opgaver, cirka 2 t 10 min
Hvem giver hvad til hvem
Every arrow is a figure or a document that reaches your desk or leaves it, and the task where that happens.
Kommer til dig
- Project managerYour firm
- Cost to completeOpgave 1
- ReforecastOpgave 4
- The ownerOwner
- Change orders, signed and unsignedOpgave 2
- SuperintendentYour firm
- Stairs delivered, not installedOpgave 3
Går fra dig
- CVR month 2026-10Opgave 1
- Earned revenue and gross profitOpgave 2
- Over/under billingOpgave 3
- Loss provisionOpgave 4
Din vej gennem sagen
Two tasks build the WIP line, one checks it against stored material and billing, one tests it against a loss. Start with task 1: from the job cost report you work out cost to date, the forecast final cost and the percent complete.
The WIP line
Opgave 1 · 30 min
Omkostninger til dato, estimat ved færdiggørelse, færdiggørelsesgrad
- Du leverer
- Cost to date, estimate at completion, percent complete
- Dokument
- Job cost report, October 2026
- I ERP
- Cost-Value Reconciliation
The WIP line
Opgave 2 · 30 min
Optjent omsætning og bruttofortjeneste
- Du leverer
- Contract value, earned revenue and both gross profits
- Dokument
- Contract sum and change orders CO-01 to CO-03
- I ERP
- Cost-Value Reconciliation, REV head
Billing check
Opgave 3 · 35 min
Ikke-installerede materialer og over-/underfakturering
- Du leverer
- Revenue with the stairs at cost, and the billing position
- Dokument
- AIA G702, pay application 9 (the monthly bill)
- I ERP
- Cost-Value Reconciliation, Edit cost head
Reforecast
Opgave 4 · 35 min
Et tabsprojekt: hele tabet nu
- Du leverer
- The provision for anticipated loss (the whole expected loss, booked now)
- Dokument
- Reforecast before the close
- I ERP
- Cost-Value Reconciliation, LOSS head
How cost turns into revenue on a WIP line
Each bar is one task, in the order the October close runs.
Blå er det, opgaven tilføjer; grå er overført fra før.
Kort sagt. Cost against cost for the percent. Stored material at cost, no margin. Gross billings against earned revenue. A loss goes in whole, the month you see it.