معرفی دوره · 3 دقیقه
جدول WIP: درصد پیشرفت و صورتحساب بیش/کم از حد (ایالات متحده)
You are the project accountant at a general contractor building a block of shops with apartments above. Each month the firm reports every open job on one line of its work-in-progress (WIP) schedule, which banks and bonding companies read. In four tasks you close October for this job: how complete it is, how much revenue it has earned, whether billing runs ahead of the work, and the loss the new forecast reveals.
پروژهٔ خیالی- Building
- Three stories: retail on a concrete podium, two wood-frame apartment floors
- Contract
- AIA A101 stipulated sum (one fixed price) with A201 general conditions; revenue counted under ASC 606
- Period
- October 2026 month-end close
- کار در ERP
- 4 تکلیف، حدود 2 ساعت 10 دقیقه
چه کسی چه چیزی به چه کسی میدهد
Every arrow is a figure or a document that reaches your desk or leaves it, and the task where that happens.
به شما میرسد
- Project managerYour firm
- Cost to completeتکلیف 1
- Reforecastتکلیف 4
- The ownerOwner
- Change orders, signed and unsignedتکلیف 2
- SuperintendentYour firm
- Stairs delivered, not installedتکلیف 3
از شما میرود
- CVR month 2026-10تکلیف 1
- Earned revenue and gross profitتکلیف 2
- Over/under billingتکلیف 3
- Loss provisionتکلیف 4
مسیر شما در پروژه
Two tasks build the WIP line, one checks it against stored material and billing, one tests it against a loss. Start with task 1: from the job cost report you work out cost to date, the forecast final cost and the percent complete.
The WIP line
تکلیف 1 · 30 دقیقه
هزینه تا امروز، برآورد هزینه در زمان تکمیل، درصد پیشرفت
- خروجی شما
- Cost to date, estimate at completion, percent complete
- سند
- Job cost report, October 2026
- در ERP
- Cost-Value Reconciliation
The WIP line
تکلیف 2 · 30 دقیقه
درآمد تحققیافته و سود ناخالص
- خروجی شما
- Contract value, earned revenue and both gross profits
- سند
- Contract sum and change orders CO-01 to CO-03
- در ERP
- Cost-Value Reconciliation, REV head
Billing check
تکلیف 3 · 35 دقیقه
مصالح نصبنشده و صورتحساب بیشتر یا کمتر از حد
- خروجی شما
- Revenue with the stairs at cost, and the billing position
- سند
- AIA G702, pay application 9 (the monthly bill)
- در ERP
- Cost-Value Reconciliation, Edit cost head
Reforecast
تکلیف 4 · 35 دقیقه
پروژه زیانده: کل زیان همین حالا
- خروجی شما
- The provision for anticipated loss (the whole expected loss, booked now)
- سند
- Reforecast before the close
- در ERP
- Cost-Value Reconciliation, LOSS head
How cost turns into revenue on a WIP line
Each bar is one task, in the order the October close runs.
آبی چیزی است که تکلیف اضافه میکند؛ خاکستری از مرحلهٔ قبل آمده است.
بهطور خلاصه. Cost against cost for the percent. Stored material at cost, no margin. Gross billings against earned revenue. A loss goes in whole, the month you see it.