WIP хуваарь: гүйцэтгэлийн хувь ба илүү/дутуу нэхэмжлэх (АНУ)
You are the project accountant at a general contractor building a block of shops with apartments above. Each month the firm reports every open job on one line of its work-in-progress (WIP) schedule, which banks and bonding companies read. In four tasks you close October for this job: how complete it is, how much revenue it has earned, whether billing runs ahead of the work, and the loss the new forecast reveals.
Зохиомол төсөл- Building
- Three stories: retail on a concrete podium, two wood-frame apartment floors
- Contract
- AIA A101 stipulated sum (one fixed price) with A201 general conditions; revenue counted under ASC 606
- Period
- October 2026 month-end close
- ERP дээрх ажил
- Даалгавар: 4, ойролцоогоор 2 цаг 10 мин
Хэн хэнд юу дамжуулдаг
Every arrow is a figure or a document that reaches your desk or leaves it, and the task where that happens.
Танд ирдэг
- Project managerYour firm
- Cost to completeДаалгавар 1
- ReforecastДаалгавар 4
- The ownerOwner
- Change orders, signed and unsignedДаалгавар 2
- SuperintendentYour firm
- Stairs delivered, not installedДаалгавар 3
Танаас гардаг
- CVR month 2026-10Даалгавар 1
- Earned revenue and gross profitДаалгавар 2
- Over/under billingДаалгавар 3
- Loss provisionДаалгавар 4
Төслөөр явах таны зам
Two tasks build the WIP line, one checks it against stored material and billing, one tests it against a loss. Start with task 1: from the job cost report you work out cost to date, the forecast final cost and the percent complete.
The WIP line
Даалгавар 1 · 30 мин
Өнөөдрийг хүртэлх зардал, дуусгалтын тооцоот зардал, гүйцэтгэлийн хувь
- Үр дүн
- Cost to date, estimate at completion, percent complete
- Баримт бичиг
- Job cost report, October 2026
- ERP дээр
- Cost-Value Reconciliation
The WIP line
Даалгавар 2 · 30 мин
Олсон орлого ба нийт ашиг
- Үр дүн
- Contract value, earned revenue and both gross profits
- Баримт бичиг
- Contract sum and change orders CO-01 to CO-03
- ERP дээр
- Cost-Value Reconciliation, REV head
Billing check
Даалгавар 3 · 35 мин
Суулгаагүй материал ба илүү/дутуу нэхэмжлэл
- Үр дүн
- Revenue with the stairs at cost, and the billing position
- Баримт бичиг
- AIA G702, pay application 9 (the monthly bill)
- ERP дээр
- Cost-Value Reconciliation, Edit cost head
Reforecast
Даалгавар 4 · 35 мин
Алдагдалтай ажил: бүх алдагдал одоо
- Үр дүн
- The provision for anticipated loss (the whole expected loss, booked now)
- Баримт бичиг
- Reforecast before the close
- ERP дээр
- Cost-Value Reconciliation, LOSS head
How cost turns into revenue on a WIP line
Each bar is one task, in the order the October close runs.
Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.
Товчхондоо. Cost against cost for the percent. Stored material at cost, no margin. Gross billings against earned revenue. A loss goes in whole, the month you see it.