OpenConstruction Academy
Sign in / Register
EN

Stage 6 of 7 · Build

Budget and cost control, earned value

Compare budget, committed and actual cost with progress to forecast the final cost.

Cost value reconciliation report with cost heads, forecast and variance
Control cost against value Cost value reconciliation report with cost heads, forecast and variance
Output
Monthly cost report with forecast final cost and earned value
Module
Cost control, EVM and risk
Documents
  • Cost report
  • Cost value reconciliation (CVR)
  • Earned value report
Standards and references
  • ISO 21508
  • EIA-748

What it is

Cost control compares what the work should cost with what it is costing and what it is forecast to cost at completion. It brings together the budget, committed costs from orders and subcontracts, actual costs from invoices and timesheets, and the value of work done. Earned value management adds a consistent way to measure performance, comparing planned value, earned value and actual cost to show cost and schedule variance.

The output is a forecast that management can act on. A cost report that only shows money spent tells nothing about the final outcome. Regular cost-value reconciliation reveals loss-making packages early, while there is still time to correct them. On the client side cost control protects the budget and informs decisions on change; on the contractor side it protects margin and cash.

Who does it

Quantity surveyor or cost manager
Prepares the monthly cost report, cost-value reconciliation and forecast.
Project manager
Explains variances and takes action to recover cost or time.
Planner
Supplies progress and planned value so earned value can be calculated.
Finance
Provides actual costs and ensures they are correctly coded.
Commercial director or client
Reviews forecasts, risk and contingency across projects.

How it runs

  1. Load the budget

    Transfer the approved estimate into the budget at cost code level, with contingency held separately.

  2. Record commitments

    Capture orders and subcontracts as committed cost against the right codes.

  3. Capture actuals

    Bring in invoices, labour and plant costs each period, checked for coding errors.

  4. Measure progress

    Record work done so earned value can be compared with actual cost and planned value.

  5. Reconcile cost and value

    Compare cost to date with value earned, including accruals for work done but not invoiced.

  6. Forecast final cost

    Estimate cost to complete for each package and add known risks and changes.

  7. Report and act

    Report variances with explanations and agreed actions, and track the actions next period.

How it differs by country

United Kingdom
Contractors commonly run a monthly cost-value reconciliation (CVR) on each project. Under NEC4 options C and D, the target cost options, defined cost and the contractor's share are tracked closely.
Germany
On the client side DIN 276 provides the structure for cost control through the design stages and Kostenfeststellung at completion. HOAI requires the architect to carry out cost control (Kostenkontrolle) in several work stages.
France
The maître d'oeuvre monitors costs against the contract amount and reports on the décompte, while contractors track margin by lot internally. Price revision by published indices is common and must be forecast.
United States
Earned value management is standardised in ANSI/EIA-748 and required on many federal projects. Contractors often track committed and actual cost by CSI MasterFormat division.
International
Lenders and owners on international projects often ask for earned value reporting with S-curves. Under FIDIC contracts the cost report must allow for variations, price adjustment and claims in progress.

Common mistakes

  • Reporting actual cost against budget without allowing for commitments and accruals.
  • Measuring progress by money spent rather than by work done.
  • Spending contingency without recording why, so the remaining risk cover is unknown.
  • Leaving unagreed changes out of the forecast because they are not yet approved.
  • Producing reports nobody acts on, with no owner or deadline for corrective actions.

In OpenConstructionERP

Module: Cost control, EVM and risk

OpenConstructionERP supports cost control through the Finance module for budgets, invoicing, payments and earned value. Full EVM adds forecasting, S-curves and TCPI analysis, and the 5D Cost Model combines budget tracking with cash flow projection. Cost-Value Reconciliation & Cashflow runs the monthly comparison of cost against value earned. Project Controls gives an executive read-only view of cost, schedule, risk and change, and the Risk Register scores risks and tracks mitigation so contingency is tied to real exposures.

Finance · Full EVM · 5D Cost Model · Cost-Value Reconciliation & Cashflow · Project Controls · Risk Register

The app runs at openconstructionacademy.com/app for course learners.

Cost value reconciliation report with cost heads, forecast and variance
Control cost against value Cost value reconciliation report with cost heads, forecast and variance

Free videos

18 videos

Courses

Checklists

Short checklists that go with this process.

Practise it in OpenConstructionERP

The free videos explain the process. The full course lets you run it yourself in the ERP, task by task.